Question #: 69
Topic #: 1
[All PMP Questions]

An agile team is working on a project that will be launched in six countries. Each country has specific requirements in addition to the base offering. The estimates indicate it will take six months to develop the base offering and an additional month to finalize each country's unique requirements. The expected revenue for the product is the same for each country.
Which release strategy should the project manager recommend?

  • A. An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country
  • B. A financial-based strategy to reduce the roll-out effort and costs by planning a single, bundled release to all countries at the same time
  • C. A risk-based strategy to maximize the perceived value of the product by launching it to the countries with the lowest technical complexity
  • D. A quality-based strategy to maximize post-market adoption by releasing the product to the countries with the lowest probability of reporting field issues
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mirou
1 month, 1 week ago
Selected Answer: A
maximizing the value is the keyword
upvoted 1 times
...
martinx84
3 months, 1 week ago
Selected Answer: A
Iterative based
upvoted 1 times
...
Lhenica
9 months, 3 weeks ago
Selected Answer: A
A most fit
upvoted 1 times
...
Muntadher
1 year, 2 months ago
Selected Answer: A
A most fit
upvoted 1 times
...
Jamrock
1 year, 2 months ago
Selected Answer: A
A. is the correct answer but in reality the consulting firm (SI) with the lowest bid will recommend a big bang approach (at best two phases - global and then all countries at once) which will be too aggressive and either lead to delayed go-lives over several years or going live on time with ridiculous amount of bugs angering the client and SI's staff where many leave if able to. At least, in the good ole USA that is how it works. Oh and the SI will tout it as a success internally. If lucky they will will actually do it in increments but that would be after replanning and new leadership being pulled in to convince everyone that is the right course of action.
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: A
A. An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country
upvoted 1 times
...
NatieRouge
1 year, 6 months ago
Why A, but not D?
upvoted 3 times
...
Ganzee
1 year, 9 months ago
A. An iterative-based strategy to maximize value by releasing the product to each country as it is finalized and ready for release in that country
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...