One phase of a project took much longer than initially anticipated. The key stakeholders expressed their concern regarding a potential project delay.
What should the project manager do?

  • A. Request additional contingency from the sponsor
  • B. Add more float to the overall project schedule
  • C. Expedite the next phase to reduce slippage
  • D. Organize a root cause analysis (RCA) workshop
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mirou
1 month, 1 week ago
Selected Answer: D
first perform RCA, them decide which way to go, more float/expdite next phase etc..
upvoted 1 times
...
BuviD
8 months, 3 weeks ago
Selected Answer: C
C. Expedite the next phase to reduce slippage
upvoted 1 times
...
Tuanit
11 months, 3 weeks ago
Selected Answer: D
I chose D
upvoted 1 times
...
Ifyy
12 months ago
I chose B. The float approach. I wonder why that is not correct
upvoted 1 times
...
SteAle
1 year, 2 months ago
Selected Answer: D
First, its important to understand the root cause of the slippage. Otherwise, the project team might run into the same issue in the next phase.
upvoted 4 times
...
Drogbadrog
1 year, 3 months ago
Selected Answer: D
If the root cause is not identified, it may reoccur in the next phase
upvoted 1 times
...
AlekhyaT
1 year, 3 months ago
D. Solution may not be always expediting the next phase. First need to assess the root cause and then take action.
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: D
D. Organize a root cause analysis (RCA) workshop
upvoted 1 times
...
JYKL88
1 year, 4 months ago
Selected Answer: D
prefer D. Need to know what the cause of the delay is before taking action.
upvoted 1 times
...
AP2023S
1 year, 4 months ago
Selected Answer: D
I dont' like C because we are talking about "potential delay" so it doesn't mean that we are late. So we don't need to rush.
upvoted 2 times
...
DavisXander
1 year, 5 months ago
Selected Answer: C
C is correct
upvoted 2 times
...
Red_Apple1
1 year, 7 months ago
Selected Answer: C
I think C
upvoted 2 times
...
Ganzee
1 year, 9 months ago
D. Organize a root cause analysis (RCA) workshop
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...