Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 67 discussion

Actual exam question from PMI's PMP
Question #: 67
Topic #: 1
[All PMP Questions]

Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised.
What should the project manager do to ensure success of the project?

  • A. Review and prioritize new requirements with stakeholders to determine which change requests are needed.
  • B. Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements.
  • C. Escalate the issue to the project sponsor and seek support to keep the original requirements.
  • D. Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
terryp
Highly Voted 1 year, 9 months ago
Selected Answer: A
A: Need a change request, first to amend the existing requirements and accept the new req.
upvoted 5 times
...
LotToLearn
Most Recent 2 months ago
A : As usually when such question come what should project manager do next always think for 1st next small step .
upvoted 1 times
...
ThanhHV7
5 months ago
Selected Answer: A
A. Review and prioritize new requirements with stakeholders to determine which change requests are needed.
upvoted 1 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: A
A. Review and prioritize new requirements with stakeholders to determine which change requests are needed.
upvoted 1 times
...
JackyHGWG
11 months ago
D. Not allowed to change even though the key stakeholders are changed.
upvoted 1 times
...
victory108
1 year, 6 months ago
Selected Answer: A
A. Review and prioritize new requirements with stakeholders to determine which change requests are needed
upvoted 1 times
...
Ganzee
1 year, 11 months ago
D. Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...