Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised. What should the project manager do to ensure success of the project?
A.
Review and prioritize new requirements with stakeholders to determine which change requests are needed.
B.
Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements.
C.
Escalate the issue to the project sponsor and seek support to keep the original requirements.
D.
Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project.
D. Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
terryp
Highly Voted 1 year, 9 months agoLotToLearn
Most Recent 2 months agoThanhHV7
5 months agoBuviD
10 months, 3 weeks agoJackyHGWG
11 months agovictory108
1 year, 6 months agoGanzee
1 year, 11 months ago