A project manager is beginning a new project with very diverse team members. The project manager chose to use consensus building so the team can agree on and be engaged in how the project will be executed. How should the project manager proceed?
A.
Create an environment where the agreement is reached by a majority vote
B.
Create an environment where the agreement is reached through discussion
C.
Establish recurring brainstorming sessions to discuss project issues
D.
Allow team members to contribute ideas in a stream-of-consciousness mode
B. Create an environment where the agreement is reached through discussion.
Consensus building involves creating an environment where team members can discuss and agree on the execution of the project. The project manager should encourage open communication and active listening among team members to ensure that everyone's ideas and concerns are heard and addressed.
Consensus building is based on the principles of local participation and ownership of decisions. Ideally, the consensus reached will meet all of the relevant interests of stakeholders, who thereby come to a unanimous agreement.
C. Establish recurring brainstorming sessions to discuss project issues
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Hung1
Highly Voted 1 year, 7 months agokevzzz
Highly Voted 1 year, 8 months agocrypto_dreams_medellin
Most Recent 1 week, 6 days agoBuviD
10 months, 3 weeks agoSULTANFS
10 months, 3 weeks agovictory108
1 year, 6 months agoAnna12675
1 year, 6 months agoGanzee
1 year, 11 months ago