A project is 70% complete when the project sponsor requests an additional deliverable.
What should the project manager do first?

  • A. Negotiate with the project sponsor on the possible alternatives
  • B. Determine the possible impact of this change on all aspects of the project
  • C. Reject the request as being too late and leading to major scope creep
  • D. Submit the request to the change control board (CCB) for a decision
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Princessviv96
1 week, 4 days ago
Selected Answer: B
My thought process is first the determine the impact of the suggested additional changes after which the project manager can now decide whether to accept or decline being that we have gone far within the project phases and any additional changes changes with evaluation could lead to scope creep
upvoted 1 times
...
Selected Answer: B
impacts, and accept changes even late in the game
upvoted 1 times
...
LotToLearn
6 months, 2 weeks ago
B as first small step
upvoted 1 times
...
BuviD
1 year, 3 months ago
Selected Answer: B
B. Determine the possible impact of this change on all aspects of the project
upvoted 2 times
...
Lhenica
1 year, 4 months ago
Selected Answer: B
Assessing first before changes execute
upvoted 1 times
...
GabMonterey
1 year, 4 months ago
Selected Answer: B
B. before executing the changes it must be assessed by how much will impact the project.
upvoted 1 times
...
Muntadher
1 year, 8 months ago
Selected Answer: B
b most fit
upvoted 1 times
...
victory108
1 year, 11 months ago
Selected Answer: B
B. Determine the possible impact of this change on all aspects of the project
upvoted 1 times
...
Anna12675
1 year, 11 months ago
Selected Answer: B
b vote
upvoted 1 times
...
Faozi
1 year, 11 months ago
Selected Answer: B
PM should first perform a review before making a decission.
upvoted 1 times
...
Selected Answer: B
The first step is to determine the possible impact.
upvoted 1 times
...
terryp
2 years, 1 month ago
Selected Answer: B
B - First review impact and if needed only then request to CCB
upvoted 1 times
...
Ade1981
2 years, 3 months ago
B is correct. PM has to do a review first.
upvoted 1 times
...
_D_S_
2 years, 3 months ago
B is right answer. PM should first assess and the take action. D is second step
upvoted 1 times
D is not 2nd step. D possibly be 2nd step after assessing its impacts.
upvoted 1 times
...
...
Ganzee
2 years, 3 months ago
D. Submit the request to the change control board (CCB) for a decision
upvoted 1 times
PMPStudent69
2 years, 2 months ago
Before it's necessary do an impact analysis, so B
upvoted 2 times
...
Key word here is First.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago