Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 47 discussion

Actual exam question from PMI's PMP
Question #: 47
Topic #: 1
[All PMP Questions]

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the quality standards required by regulations.
What should the project manager have done to avoid this?

  • A. Ensured that the project sponsor understood the scope of the project to avoid any future complaints
  • B. Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks
  • C. Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration
  • D. Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
fragar65
1 month, 2 weeks ago
C is proactive, hence, the answer. B is after the fact, it is already too late.
upvoted 1 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: B
B. Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks
upvoted 4 times
...
Lhenica
11 months, 3 weeks ago
Selected Answer: C
Need to review acceptance criteria
upvoted 3 times
...
GabMonterey
11 months, 4 weeks ago
Selected Answer: C
C. as you need to check the acceptance criteria before releasing it.
upvoted 1 times
...
SteAle
1 year, 5 months ago
Selected Answer: C
C. PM needs to review the agreed upon acceptance criteria.
upvoted 2 times
...
victory108
1 year, 6 months ago
Selected Answer: C
C. Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration
upvoted 1 times
...
Faozi
1 year, 7 months ago
Selected Answer: C
Anwer is C
upvoted 1 times
...
shaharyarexamtopics
1 year, 8 months ago
Selected Answer: C
Quality Standards should be built-in into acceptance criteria.
upvoted 2 times
...
Najlaaabbas
1 year, 8 months ago
Project management requires assertive communication
upvoted 1 times
...
achacyrille
1 year, 8 months ago
Selected Answer: C
We audit processes to make sure organizational procedures, processes and policies are respected , and perform quality control on deliverables to make sure they meet acceptance criteria defined during the initiation phase of the project and quality standards defined during the planning phase.
upvoted 2 times
...
6thEditionAndy
1 year, 9 months ago
Selected Answer: C
Quality and law requglations are part of the Acceptance criteria
upvoted 3 times
...
terryp
1 year, 9 months ago
Selected Answer: C
Answer C - ensured acceptance criteria were met for the user stories.
upvoted 3 times
...
PMPStudent69
1 year, 10 months ago
Selected Answer: B
The quality compliance is managed by the Agile team. the PM or PO didn't check the quality standard. the quality is on chargr the team.
upvoted 4 times
...
Ganzee
1 year, 11 months ago
C. Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...