A new major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings.
Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.
What should the project manager do first?
PMPStudent
Highly Voted 1 year, 11 months agocrypto_dreams_medellin
Most Recent 1 week, 6 days agoLotToLearn
1 month, 3 weeks agoPragati06
2 months agonzili
7 months, 1 week agoBuviD
10 months, 3 weeks agoGabMonterey
11 months, 3 weeks agoNelsned
1 year, 2 months agovictory108
1 year, 6 months agoAnna12675
1 year, 6 months agoKRISHLM
1 year, 6 months agoshaharyarexamtopics
1 year, 8 months agoCert_IT
1 year, 11 months agoGanzee
1 year, 11 months agoshaharyarexamtopics
1 year, 8 months ago