A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.
What should the project manager do?
achacyrille
Highly Voted 2 years, 1 month agoJamrock
1 year, 7 months agokavikris
4 months, 1 week agoDinesh1987
Highly Voted 2 years, 1 month agoPrincessviv96
Most Recent 1 week, 5 days agocrypto_dreams_medellin
5 months agocrypto_dreams_medellin
5 months agoArailym
7 months agosweety433
10 months, 1 week agoBhanu2086
11 months, 3 weeks agokraze29
1 year, 2 months agoBuviD
1 year, 3 months agoBuviD
1 year, 3 months agoThienDo93
1 year, 3 months agoGabMonterey
1 year, 4 months agoRajj98
1 year, 4 months agoPranav2204
1 year, 6 months agoNjabz_10
1 year, 8 months agoJamrock
1 year, 7 months agoSteAle
1 year, 9 months agoJamrock
1 year, 7 months ago