exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 40 discussion

Actual exam question from PMI's PMP
Question #: 40
Topic #: 1
[All PMP Questions]

A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.
What should the project manager do?

  • A. Discuss with the customer the risks identified and team's concerns
  • B. Discuss with the team, estimate the effort, and raise a change request
  • C. Ask the customer to go live and add the new functionality in the backlog
  • D. Ask the team to deliver the functionality on the agreed go-live date
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
achacyrille
Highly Voted 1 year, 9 months ago
Selected Answer: A
The risk has already been identified, evaluated by the project team and its impact already determined as to have conflit with the scope. The next thing to do is to inform the customer and discuss raised concerns with him on the impact this change will have on the scope.
upvoted 16 times
Jamrock
1 year, 3 months ago
should be B. analyze, raise CR and goes through the process. no autocratic decisions: A. Discuss with the customer the risks identified and team's concerns. While it is important to discuss the risks and concerns with the customer, it is not sufficient to address the situation fully. The project manager needs to involve the team, estimate the effort, and formally document the change request.
upvoted 3 times
kavikris
3 weeks, 1 day ago
Answer A, - Think once, what if the teams estimate says 1 month delay and customer says he is fine not to have the added functionality instead going live with original schedule is far more important? simply adding every customer request to change request without discussing the implications and risks with customer isnt the right approach, hence answer should be A
upvoted 1 times
...
...
...
Dinesh1987
Highly Voted 1 year, 9 months ago
Selected Answer: B
In this scenario, the project team has identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope. Therefore, the project manager should discuss the situation with the team to assess the impact of the change, estimate the effort required to implement the new functionality, and evaluate the risks and benefits of approving the change request. Then, the project manager should raise a change request to the customer and seek their approval before proceeding with the change.
upvoted 8 times
...
crypto_dreams_medellin
Most Recent 1 month, 2 weeks ago
we are not going to raise a change request when we have not resolved the risks, the issues need to be resolved before it is turned into a story to be worked, it must not be added to the back log till issues identified and resolved....
upvoted 1 times
...
crypto_dreams_medellin
1 month, 2 weeks ago
Selected Answer: A
A: communicate with the customer the risk the team found, the requirement is ad hoc, and needs to be discussed, and then prioritized based on business value. must follow a normal process
upvoted 2 times
...
Arailym
3 months, 1 week ago
Discuss with the team, estimate the effort, and raise a change request
upvoted 1 times
...
sweety433
6 months, 2 weeks ago
Answer is A : Discuss with the customer the risks identified and team's concerns. This option is the best course of action because it involves directly addressing the customer's request while also communicating the potential risks and concerns raised by the project team. This step ensures that the customer is fully aware of the implications of their request, including the impact on the delivery date and any conflicts with the agreed scope. It allows for an informed decision to be made collaboratively, which is essential in maintaining a good client relationship and ensuring the success of the project. This approach also aligns with the PMP best practices of managing stakeholder expectations and engaging in effective communication.
upvoted 4 times
...
Bhanu2086
8 months ago
Selected Answer: A
The risk identified and the associated impact should be discussed with the customer along with scope creep concerns. Even after this, if the customer wants to go ahead with the reqs, then a CR should be raised and change control process should be followed.
upvoted 3 times
...
kraze29
11 months, 1 week ago
Selected Answer: A
Option A, discussing with the customer the risks identified and team’s concerns, seems to be the most appropriate. This approach ensures that the customer is fully aware of the implications of their request and can make an informed decision.
upvoted 1 times
...
BuviD
11 months, 3 weeks ago
Selected Answer: A
Discuss with the customer the risks identified and team's concerns
upvoted 1 times
...
BuviD
11 months, 3 weeks ago
Selected Answer: C
C. Ask the customer to go live and add the new functionality in the backlog
upvoted 1 times
...
ThienDo93
11 months, 3 weeks ago
Selected Answer: A
The key is "the requested functions are in conflict with the agreed scope"; if not conflict, you can evaluated and raise change request, but it is conflicted, then you should to identify and make it clear with the customer first. May customer did not recognize the conflict, if they know, they have not required it yet.
upvoted 1 times
...
GabMonterey
1 year ago
Selected Answer: A
A. Giving the customer the impact of the changes or additional scope.
upvoted 1 times
...
Rajj98
1 year, 1 month ago
Answer is B - Assess and raise a change request. Change Control Board will review and approve or reject!!
upvoted 1 times
...
Pranav2204
1 year, 3 months ago
Selected Answer: B
B is the ans
upvoted 1 times
...
Njabz_10
1 year, 4 months ago
A is the correct answer since the requests are not in line with the scope therefore you cannot opt for B and estimate efforts of something that totally contradicts the main deliverables.
upvoted 1 times
Jamrock
1 year, 3 months ago
should be B. analyze, raise CR and goes through the process. no autocratic decisions: A. Discuss with the customer the risks identified and team's concerns. While it is important to discuss the risks and concerns with the customer, it is not sufficient to address the situation fully. The project manager needs to involve the team, estimate the effort, and formally document the change request.
upvoted 1 times
...
...
SteAle
1 year, 6 months ago
Selected Answer: A
A - The project manager should first understand the customer's request. The next step would be to assess the impact (B)
upvoted 1 times
Jamrock
1 year, 3 months ago
should be B. analyze, raise CR and goes through the process. no autocratic decisions: A. Discuss with the customer the risks identified and team's concerns. While it is important to discuss the risks and concerns with the customer, it is not sufficient to address the situation fully. The project manager needs to involve the team, estimate the effort, and formally document the change request.
upvoted 1 times
...
...
rknowles
1 year, 6 months ago
Selected Answer: A
I am going with A because of one small wording issue with B. 'Raise a change request' in option B would not be the right course of action. It's the PM's responsibility to first evaluate the impact of the change to the project. In this case it could negatively impact the schedule and deviates from the original scope so shouldn't the PM speak with the customer first prior to submitting the change request?
upvoted 2 times
Jamrock
1 year, 3 months ago
should be B. analyze, raise CR and goes through the process. no autocratic decisions: A. Discuss with the customer the risks identified and team's concerns. While it is important to discuss the risks and concerns with the customer, it is not sufficient to address the situation fully. The project manager needs to involve the team, estimate the effort, and formally document the change request.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago