A project team is implementing a hosted system for a third party. Just before going live, the customer asks the project team to include additional functionality. The project team identified risks to the delivery date and informed the project manager that some of the requested functions are in conflict with the agreed scope.
What should the project manager do?
achacyrille
Highly Voted 1 year, 8 months agoJamrock
1 year, 2 months agoDinesh1987
Highly Voted 1 year, 8 months agocrypto_dreams_medellin
Most Recent 2 weeks agocrypto_dreams_medellin
2 weeks agoArailym
2 months, 1 week agosweety433
5 months, 2 weeks agoBhanu2086
7 months agokraze29
10 months, 1 week agoBuviD
10 months, 3 weeks agoBuviD
10 months, 3 weeks agoThienDo93
10 months, 3 weeks agoGabMonterey
11 months, 3 weeks agoRajj98
1 year agoPranav2204
1 year, 2 months agoNjabz_10
1 year, 3 months agoJamrock
1 year, 2 months agoSteAle
1 year, 4 months agoJamrock
1 year, 2 months agorknowles
1 year, 5 months agoJamrock
1 year, 2 months ago