A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met. What should the project manager do?
A.
Discuss and agree with the customer to implement the missing requirement
B.
Refer to the requirements traceability matrix and analyze the requirement
C.
Consult the scope management plan with the customer to understand the gap
D.
Analyze the benefits management plan and implement the needed change
Requirement not met means it was already defined in planning during Define Requirement Process before Create Scope Statement Process. A requirment traceability matrix should be consulted to have more information on this requirment and how it is linked to other artifacts of the project.
In my opinion Bis the correct line faction for this scenario, revisiting the requirements traceability matrix plan would enable the team trace any gaps and clearly realign with the clients on areas where the requirements weren't met b
Scope management plan is created BEFORE requirements are collected. This means scope management plan doesn't have any info about specific requirements.
The scope management plan collects requirements from whom the project is going to deliver value to, (the customer) if its not a high level requirement, then C will be the answer. If its a high level requirement, then it will be B........it just said a requirement is missing, and he or she is mad, so I would have to pick C
requirements traceability matrix will link the requirement and where it came from and will influence scope. If the customer required a certain requirement, it will be there, and it can be studied.
Requirement not met means it should be in requirement traceability matrix as defined requirement so need to revisit the document again.Answer should be B
Answer B : The requirements traceability matrix (RTM) is a tool that helps track the status of project requirements throughout the project lifecycle. By referring to the RTM, the project manager can verify if the requirement was documented, approved, and if it was planned to be delivered.
The project manager should B. Refer to the requirements traceability matrix and analyze the requirement. This matrix helps track the relationship between project requirements and their sources, ensuring that all requirements are addressed. By analyzing the requirement in question, the project manager can identify the gap and determine the appropriate course of action to address it. It’s essential to communicate transparently with the customer and work towards a resolution.
When the customer arrived at the project site, they discovered that one of their requirements was not met. This means requirements were already defined. Discuss and agree with the customer to implement a missing requirement is the immediate action that can be taken.
B: The requirement traceability matrix is a table that is created to link the requirements back to their origin. The traceability basically tracks where the requirement suggestion came from, which stakeholder gave the requirement, and why it was added to the actual project. It will help to keep track of the requirements as the project is carried out.
I think you are misunderstand. Requirement traceability matrix link requirement from their origin to "deliverables". It shows that the deliverables satisfy which requirements and ensures that requirements are delivered at the end of the project. Not "origin" as you are explaining.
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
achacyrille
Highly Voted 2 years, 1 month agoPrincessviv96
Most Recent 1 week, 5 days agoK91
3 months, 2 weeks agocrypto_dreams_medellin
5 months agocrypto_dreams_medellin
5 months agocrypto_dreams_medellin
5 months agoZubair1
5 months, 1 week agoPragati06
6 months, 3 weeks agosweety433
10 months, 1 week agoakashushi007
11 months agohoomz
1 year, 1 month agokraze29
1 year, 2 months agoBuviD
1 year, 3 months agoDeeski
1 year, 3 months agohonidt
1 year, 1 month agoGabMonterey
1 year, 4 months agoTuanit
1 year, 6 months agoPranav2204
1 year, 6 months ago