Actual exam question from PMI's PMP
Question #: 31
Topic #: 1
[All PMP Questions]

A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.
What should the project manager do first?

  • A. Assess the time overrun, and start implementation to avoid additional delays
  • B. Motivate the team to avoid the frustration of working on a prolonged project
  • C. Request a provisional budget increase to avoid any budget overruns
  • D. Review the benefits of the proposed changes in relation to the business case
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
D: the vision is poor, many changes, will the changes deliver value or just a waste of time, we don't know, so we need to do research and review the benefits and business case.
upvoted 1 times
...
Mgaidiwahid
1 month, 3 weeks ago
Selected Answer: D
D is the best option
upvoted 1 times
...
Amirov
2 months ago
Selected Answer: D
D is the best option
upvoted 1 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: D
D. Review the benefits of the proposed changes in relation to the business case
upvoted 1 times
...
GabMonterey
11 months, 3 weeks ago
Selected Answer: D
D is most fitted asnwer
upvoted 1 times
...
Pranav2204
1 year, 2 months ago
Selected Answer: D
D is answer
upvoted 1 times
...
Aymen1989
1 year, 2 months ago
I shoose d
upvoted 1 times
...
stujam
1 year, 3 months ago
D Review and assess the impact the changes may have on the project including and risk assessment
upvoted 1 times
...
Muntadher
1 year, 4 months ago
Selected Answer: D
d most fit
upvoted 1 times
...
AbbasTaki
1 year, 6 months ago
Selected Answer: D
Voted D. changes must always be assessed and analyzed before any action
upvoted 2 times
...
victory108
1 year, 6 months ago
Selected Answer: D
D. Review the benefits of the proposed changes in relation to the business case
upvoted 1 times
...
Anna12675
1 year, 6 months ago
Selected Answer: D
d is answer
upvoted 1 times
...
BenPappoe
1 year, 7 months ago
Selected Answer: B
Voted B
upvoted 1 times
...
Faozi
1 year, 7 months ago
Anwer is D
upvoted 1 times
...
mromeis
1 year, 8 months ago
Selected Answer: D
Answer is D
upvoted 1 times
...
meetkamal
1 year, 10 months ago
Selected Answer: D
It should be D
upvoted 4 times
...
Ade1981
1 year, 11 months ago
First thing is to review the change request for benefit... then he can go ahead with talk of budget or time change
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...