A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next milestone. This change can be perceived as poor performance by the current assignees.
What should the project manager do?
gspace
Highly Voted 1 year, 7 months agokazu91
Most Recent 2 months, 1 week agohihemant1509
8 months, 1 week agoBuviD
8 months, 3 weeks agoGabMonterey
9 months, 3 weeks agoMuntadher
1 year, 2 months agoSteAle
1 year, 3 months agovictory108
1 year, 4 months agoBenPappoe
1 year, 5 months agoAnna12675
1 year, 5 months agoHungdv
1 year, 6 months agoHung1
1 year, 5 months agoGanzee
1 year, 9 months ago