A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next milestone. This change can be perceived as poor performance by the current assignees.
What should the project manager do?
Ganzee
Highly Voted 2 years, 3 months agogspace
Highly Voted 2 years, 1 month agoductrinh
Most Recent 1 week, 5 days agoDeepakuc
4 months, 3 weeks agokazu91
8 months, 2 weeks agohihemant1509
1 year, 2 months agoBuviD
1 year, 3 months agoGabMonterey
1 year, 4 months agoMuntadher
1 year, 8 months agoSteAle
1 year, 9 months agovictory108
1 year, 11 months agoBenPappoe
1 year, 11 months agoAnna12675
1 year, 11 months agoHungdv
2 years agoHung1
1 year, 11 months ago