Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 26 discussion

Actual exam question from PMI's PMP
Question #: 26
Topic #: 1
[All PMP Questions]

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next milestone. This change can be perceived as poor performance by the current assignees.
What should the project manager do?

  • A. Organize a team meeting and inform the team members that, as the person accountable for delivery, they decided to change the task allocation
  • B. Ask the more experienced team member privately to take the task and inform the other team members that work has been reassigned
  • C. Ask the less experienced team member privately to stop working on the task and inform another team member that the work has been reassigned
  • D. Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
gspace
Highly Voted 1 year, 7 months ago
Option A might be worth exploring here. In the question, it says the team members are used to being told what to do + they are under a hierarchical system. Sounds like a plan driven environment.
upvoted 6 times
...
kazu91
Most Recent 2 months, 1 week ago
This change can be perceived as poor performance by the current assignees. => Current process is facing problem. We need to change, firstly is Task Allocation, and asking them support to define it.
upvoted 1 times
...
hihemant1509
8 months, 1 week ago
Selected Answer: D
D is the best answer
upvoted 1 times
...
BuviD
8 months, 3 weeks ago
Selected Answer: D
D. Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation
upvoted 1 times
...
GabMonterey
9 months, 3 weeks ago
Selected Answer: D
D is best asnwer
upvoted 1 times
...
Muntadher
1 year, 2 months ago
Selected Answer: D
D most fit
upvoted 2 times
...
SteAle
1 year, 3 months ago
D. Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation
upvoted 2 times
...
victory108
1 year, 4 months ago
Selected Answer: D
D. Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation
upvoted 1 times
...
BenPappoe
1 year, 5 months ago
Selected Answer: D
Voted D
upvoted 1 times
...
Anna12675
1 year, 5 months ago
Selected Answer: A
a or d
upvoted 1 times
...
Hungdv
1 year, 6 months ago
A or D?
upvoted 1 times
Hung1
1 year, 5 months ago
D is answer
upvoted 1 times
...
...
Ganzee
1 year, 9 months ago
D. Organize a team meeting to inform team members about a change in direction and work with them to change the task allocation
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...