Exam PMP topic 1 question 17 discussion

Actual exam question from PMI's PMP
Question #: 17
Topic #: 1
[All PMP Questions]

A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than- planned cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.
What should the project manager have done to avoid this situation?

  • A. Notified all vendors about the invoicing and nonpayment deadlines
  • B. Reviewed the total committed cost against the cost invoiced at project closing
  • C. Involved the finance team and discussed the issue with the vendor
  • D. Captured and reviewed all of the project work and related costs regularly
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Jamrock
Highly Voted 1 year, 7 months ago
Selected Answer: D
In conclusion, the correct answer, D, suggests that by regularly capturing and reviewing project work and related costs before the situation occurs, the project manager could have identified and addressed discrepancies or issues early, ultimately preventing the delayed invoice and increased costs during project handover. All other answers refer to after the problem occurs this is the only solution that addresses before a problem which is what the question asked.
upvoted 12 times
...
Princessviv96
Most Recent 3 days, 13 hours ago
Selected Answer: D
In my opinion to avoid a situation its important that every reported against a project be reviewed periodically and discrepancies sorted with the vendors immediately to avoid delay and scope creep
upvoted 1 times
...
0f95a2a
7 months, 3 weeks ago
Selected Answer: A
A seems like a better answer than D; can someone educate me?
upvoted 2 times
fragar65
5 months, 4 weeks ago
Proactive vs. Reactive. D is the best answer.
upvoted 1 times
...
...
053e3de
10 months ago
A. It suggests notifying all vendors about deadline and due dates.
upvoted 2 times
...
BuviD
1 year, 2 months ago
Selected Answer: D
D. Captured and reviewed all of the project work and related costs regularly
upvoted 1 times
...
Wilchim
1 year, 4 months ago
Selected Answer: A
The issue is not about monitoring, even if the project manager had effectively monitored and evaluated regularly, submitting an invoice when they are about to make the final closing submission would make all efforts futile. Hence ensuring that vendors are aware of deadlines and nonpayment penalties, does help prevent this.
upvoted 3 times
...
Uncle_Lucifer
1 year, 5 months ago
Selected Answer: A
No brainer A. The issue is the later report of invoice. Don't forget the theme of the question
upvoted 2 times
...
Alphy07
1 year, 6 months ago
D is correct
upvoted 1 times
...
BirdCat
1 year, 8 months ago
Selected Answer: A
Even if the PM would have been reviewing all project work and related costs, it is critical to relay invoicing and non payment deadlines. Then subsequent invoices can be disputed if necessary. Monitory cost and invoices is important, but there is no recourse for late invoices.
upvoted 4 times
...
Muntadher
1 year, 8 months ago
Selected Answer: D
D my vote.. where review freaquently
upvoted 2 times
...
victory108
1 year, 10 months ago
Selected Answer: D
D. Captured and reviewed all of the project work and related costs regularly
upvoted 3 times
...
MaxInsane
1 year, 11 months ago
VOTED D
upvoted 2 times
...
BenPappoe
1 year, 11 months ago
Selected Answer: A
Voted A
upvoted 3 times
...
Anna12675
1 year, 11 months ago
Selected Answer: D
d correct
upvoted 1 times
...
Rena1352
2 years ago
Selected Answer: D
D is correct
upvoted 1 times
...
achacyrille
2 years ago
Selected Answer: D
The main issue here is a defect in monotoring process activities. Along the project life cycle, the project manager and team have to continually perform M&C activities on cost, schedule, quality, resource, risks and scope. The scenario discribes a predictive approach with a one time deliverable at the end of the project so constant feedback from customer isn't possible. In such an approach, it's key to monitor the above contstraints regularly through out the different phases. As such continously analysing the impact on and balancing constraints in case a modification is done or a change controle process is innitiated and completed due to variances observed due to monotoring that where beyond acceptable levels.
upvoted 3 times
...
Dinesh1987
2 years ago
I think B is the answer as even if the project manager reviews the work and costs regularly, the delayed invoice could still be submitted. I think this question deals with the fact that the handover was delayed and if during closing the project manager picked up on the delayed invoice, then he could have addressed it then.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.