Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 15 discussion

Actual exam question from PMI's PMP
Question #: 15
Topic #: 1
[All PMP Questions]

A project manager is managing a large project. A stakeholder has just discovered a new risk that has not been identified in earlier stages.
What should the project manager do?

  • A. Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders
  • B. Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register
  • C. Communicate the risk to the steering committee and request a mitigation plan from senior management
  • D. Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Ganzee
Highly Voted 1 year, 11 months ago
D. Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders
upvoted 11 times
...
jankusil
Most Recent 3 weeks ago
Selected Answer: B
I'd vote for B. Stakeholder has found a risk and this needs to be understood first. So I communicate with this specific stakeholder first, and update risk register. After that, risk analysis can be done with the relevant stakeholders
upvoted 2 times
...
jankusil
3 weeks ago
I'd vote for B. Stakeholder has found a risk and this needs to be understood first. So I communicate with this specific stakeholder first, and update risk register. After that, risk analysis can be done with the relevant stakeholders
upvoted 1 times
...
Sambhav
1 month, 3 weeks ago
A. Confirm to the stakeholder that the risk register has been completed and validated by all stakeholders This option is out. Risk can be identified and added to the risk register at any time in a project life cycle. B. Perform a risk analysis directly with the stakeholder who raised the risk and update the risk register This option is out. Why we're not involving the project team when they can help to do it in a better way C. Communicate the risk to the steering committee and request a mitigation plan from senior management This option is out. This is a knee-jerk reaction, without analysing and evaluating we shouldn't bypass the process. D. Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders This is a correct option. This is a correct risk management procedure, acknowledge the risk discovery by adding to risk register and then involve project team and stakeholders to evaluate the risk
upvoted 2 times
...
oreh
2 months ago
Selected Answer: D
When a new risk is identified, the project manager should immediately add it to the risk register and involve the project team and relevant stakeholders in reevaluating the register. Risk analysis should involve the entire project team and other stakeholders to ensure a comprehensive evaluation.
upvoted 1 times
...
Deepak6464
2 months ago
Selected Answer: D
D. Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders. When a new risk is identified, the project manager should update the risk register and involve the team and stakeholders in reevaluating the risks to determine the impact and mitigation strategies. This ensures that all relevant parties are aware of the new risk and can collaboratively work on addressing it. A. Confirming that the risk register was completed and validated ignores the new information and would not adequately address the risk. B. Performing a risk analysis directly with the stakeholder is useful, but the project manager should involve the full project team to ensure all perspectives are considered. C. Communicating the risk to the steering committee and requesting a mitigation plan from senior management bypasses the project team and limits collaborative input.
upvoted 1 times
...
PM_571
3 months, 2 weeks ago
B : When a new risk is identified, the first priority is to understand the risk in detail. To do this, it is crucial to conduct a direct analysis with the stakeholder who raised the risk. This process allows for a thorough understanding of the risk, which can then be accurately documented in the risk register. This ensures that the risk is properly assessed and that appropriate actions can be taken. Therefore, B is the correct answer.
upvoted 1 times
...
053e3de
5 months, 3 weeks ago
I don't think it's okay to perform risk analysis directly with just one stakeholder and not include other stakeholders. That might cause issues in the the long run. All stakeholders should be carried along.
upvoted 2 times
...
053e3de
5 months, 3 weeks ago
By process of elimination, D seem appropriate to me.
upvoted 1 times
...
ompk
6 months, 2 weeks ago
its a common knowledge that if a team-member discovered (Identified) a new risk and informed the PM. The PM should add it to the register and evaluate/asses the potential impact of the risk in collaboration with the team and related stakeholders. so in this case D is the right answer
upvoted 1 times
...
Karan1102
7 months, 2 weeks ago
D. Adding the risk to the risk register and reevaluating the register with help from the project team and stakeholders is the most appropriate action. This approach ensures that the risk is documented and allows for a thorough assessment of the risk, its potential impact, and appropriate mitigation strategies. By involving the project team and stakeholders, the project manager can leverage their collective knowledge and expertise to better understand and manage the risk.
upvoted 1 times
...
hoomz
9 months, 2 weeks ago
D. After adding the new risk to the risk register, it is essential to reevaluate the entire register to ensure that the overall project risk assessment remains accurate and that appropriate risk response strategies are in place. This reevaluation should involve collaboration with the project team and stakeholders to leverage their expertise and insights, ensuring a comprehensive and effective approach to risk management.
upvoted 2 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: D
D. Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders
upvoted 1 times
...
Muminat
11 months ago
B is correct
upvoted 1 times
...
shaowni7
1 year, 1 month ago
Selected Answer: D
Add the risk to the risk register and reevaluate the register with help from the project team and stakeholders
upvoted 3 times
...
Tuanit
1 year, 1 month ago
Selected Answer: D
Speak with the stakeholder to understand his concern is enough, then add to risk register and perform evaluation with team and stakeholders. B seems to be correct, however it emphasizes analyzing risk directly with the stakeholder. It's too much for the stakeholder and on the other side, not enough to analyze the risk when ignoring the participation of team and other stakeholders.
upvoted 2 times
...
eyestowardsky1
1 year, 1 month ago
Selected Answer: D
I believe D is the most accurate in this scenario.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...