Exam PMP topic 1 question 7 discussion

Actual exam question from PMI's PMP
Question #: 7
Topic #: 1
[All PMP Questions]

A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities.
What should the project manager do?

  • A. Review and reassign team assignments
  • B. Facilitate communication and team building
  • C. Negotiate for new team members
  • D. Review and update the communications management plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TonyMai92
Highly Voted 1 year, 10 months ago
My idea A. Review and reassign team assignments is wrong because "Individual performance is satisfactory" B. Facilitate communication and team building is the best, as group activities performance is low and team members located in different countries and time zones, thus they need more chances to communicate, team building is a good idea. Good communicate >> good work C. Negotiate for new team members is wrong, because it's the last (bad) option if we have to do D. Review and update the communications management plan isn't the best, because you still don't know which needs to be reviewed and changed in the document and not help the team right now
upvoted 13 times
...
Aditech
Most Recent 2 months ago
B The project manager should implement strategies to enhance team cohesion and communication, such as regular virtual meetings to foster collaboration, setting clear expectations for group activities, utilizing collaboration tools, and promoting cultural understanding among team members. Additionally, they should encourage team members to share best practices and lessons learned to improve overall performance. Adigun.
upvoted 1 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: B
B. Facilitate communication and team building
upvoted 1 times
...
Ravi4french
1 year, 1 month ago
Selected Answer: B
B. Facilitate communication and team building
upvoted 1 times
...
Biggy88
1 year, 2 months ago
B is the right answer
upvoted 1 times
...
Alphy07
1 year, 2 months ago
The answer is B
upvoted 1 times
...
OruMary
1 year, 3 months ago
Selected Answer: B
Answer is B
upvoted 1 times
...
Mahi_02021988
1 year, 3 months ago
Answer is B
upvoted 1 times
...
Mbolatiana
1 year, 4 months ago
Selected Answer: B
B is correct
upvoted 1 times
...
Fela80
1 year, 5 months ago
Selected Answer: B
Since individual performance is satisfactory, and team performance is poor, then facilitating communication and team building will be the best option
upvoted 1 times
...
victory108
1 year, 6 months ago
Selected Answer: B
B. Facilitate communication and team building
upvoted 1 times
...
BenPappoe
1 year, 7 months ago
Selected Answer: B
Voted B
upvoted 1 times
...
Anna12675
1 year, 7 months ago
Selected Answer: B
b is correct
upvoted 1 times
...
Marshalooo
1 year, 8 months ago
B. Facilitate communication and team building
upvoted 1 times
...
Khaled2022
1 year, 8 months ago
B is correct
upvoted 1 times
...
RaajAli109
1 year, 8 months ago
b is right
upvoted 1 times
...
pavan555manjunath
1 year, 9 months ago
Vote D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...