Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 718 discussion

Actual exam question from PMI's PMP
Question #: 718
Topic #: 1
[All PMP Questions]

A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.

What should the project manager do to integrate the diverse stakeholder groups?

  • A. Develop a joint quality policy for the project and seek a commitment by all of the departments.
  • B. Analyze the probability and impact of the risks linked with the situation and implement the proper response plan.
  • C. Hold separate meetings with the individual stakeholders and escalate their concerns to the project sponsor.
  • D. Advise the team members to focus on project work and avoid getting distracted by the stakeholders' disagreements.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
kevzzz
Highly Voted 1 year, 4 months ago
Selected Answer: B
Diverse stakeholder groups can be a risk and need to be mitigated to build trust and support adjustments earlier in the project life cycle. Page 506 of PMBOK 6th Edition.
upvoted 9 times
...
Aish_
Highly Voted 1 year, 1 month ago
Selected Answer: A
Voting for A as the question is about integrating. Developing a joint quality policy involves collaboratively defining the project's quality expectations, standards, and processes. By involving all the stakeholders in this process, the project manager can bring clarity to the project's objectives and how it should be handled. Seeking a commitment from each department ensures that they are aligned with the project's quality goals and approach. Option B, analyzing risks and implementing a response plan, might help address specific issues related to misunderstandings and confusion, but it does not directly focus on integrating the diverse stakeholder groups and aligning their expectations.
upvoted 8 times
dinodragon
3 months, 1 week ago
Question is not just about integration .. it is about how the project should be handled. How would a 'quality' document help with the project handling? Would rather go with B
upvoted 2 times
...
...
[Removed]
Most Recent 6 months, 3 weeks ago
Selected Answer: A
Option B would not integrate diverse stakeholder groups. Option A is better, to have a common understanding for the deliverables.
upvoted 1 times
...
Trytrio
7 months, 2 weeks ago
Selected Answer: A
Its a communication issue. A. Develop a joint quality policy for the project and seek a commitment from all of the departments. To integrate diverse stakeholder groups with different expectations, it's important to establish a common understanding and commitment to the project's goals and quality standards. Developing a joint quality policy that aligns with the project's objectives and involves input from all relevant departments can help create a shared vision and expectations. This can foster collaboration and reduce confusion and misunderstandings among stakeholders. Regular communication and collaboration with stakeholders are also essential to ensure that their concerns and expectations are addressed throughout the project.
upvoted 2 times
...
bobo_d
9 months ago
Selected Answer: B
multiple stakeholders means risk
upvoted 1 times
...
cb4a6c4
9 months, 3 weeks ago
Its A. A quality policy and commitment should help integrate the stakeholders.
upvoted 1 times
...
Only12go
11 months ago
Selected Answer: C
Given the above, the best approach would be to hold comprehensive stakeholder engagement sessions where all concerns and expectations are discussed, and consensus is sought. However, since there isn't an option directly suggesting this, the closest and most proactive choice would be C: Hold separate meetings with the individual stakeholders and escalate their concerns to the project sponsor. Through individual meetings, the project manager can gather detailed insights into each stakeholder's perspective and then work collaboratively to find common ground.
upvoted 1 times
...
adingmaki
11 months, 3 weeks ago
Diversity should be seen as a strength. Not a risk.
upvoted 2 times
sweety433
2 weeks, 3 days ago
Great callout agree wth that. So I choose A
upvoted 1 times
...
ChezQW
11 months, 1 week ago
The diversity is causing conflict and can affect the project, therefore it more of a risk now and not an opportunity.
upvoted 1 times
...
...
victory108
11 months, 3 weeks ago
Selected Answer: B
B. Analyze the probability and impact of the risks linked with the situation and implement the proper response plan
upvoted 1 times
...
psvexam
1 year ago
Ans is A: Question is about "stakeholders being diverse and have different expectations". SO a common quality policy is required to get all of them onto same page.
upvoted 1 times
ChezQW
11 months, 1 week ago
Wouldn't they need to agree on the requirements before they can agree on a quality policy to ensure that the quality of the requirements are controlled and managed properly? If they cannot agree on the requirements how could they agree on a quality control policy?
upvoted 1 times
...
...
zayn_1983
1 year, 1 month ago
PM must involving all stakeholders and make decision either by voting, Multicritera decission to get the consensus among stakeholders
upvoted 1 times
...
fulcrum501
1 year, 4 months ago
A should be the correct answer since the root cause of the problem is conflicting expectations from different departments. Once alignment between the departments is achieved, then this risk/issue will be resolved.
upvoted 2 times
...
VPNalumni
1 year, 5 months ago
A should be correct. B seems not address the root cause of the problem
upvoted 2 times
...
Hung3102
1 year, 5 months ago
I choose A
upvoted 1 times
...
Alizade
1 year, 5 months ago
Selected Answer: B
The project manager should analyze the probability and impact of the risks linked with the situation and implement the proper response plan. This will help the project manager to identify and mitigate potential issues that may arise due to the diverse stakeholder groups. By doing so, the project manager will be able to create a more cohesive team environment where stakeholders feel heard, and their concerns are addressed. Additionally, this approach will help to ensure that the project stays on track and delivers the expected outcomes.
upvoted 2 times
...
Apprend7
1 year, 7 months ago
I think A is the correct answer
upvoted 3 times
...
dickytricky
1 year, 8 months ago
I would go with A.
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...