When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined.
What should the project manager do?

  • A. Forward the issue to the benefit owner and ask them to collect the missing data and build the KPIs.
  • B. Coordinate with the benefit owner to track and collect the missing data and build the KPIs.
  • C. Work with the business analysts to track and collect the missing data and build the KPIs.
  • D. Ask the program manager to track and collect the missing data and work to build the KPIs.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
josephsafiran
9 months, 2 weeks ago
Selected Answer: B
The project manager should B. Coordinate with the benefit owner to track and collect the missing data and build the KPIs. The benefit owner is typically the person who has the best understanding of the benefits and how they should be measured. By coordinating with them, the project manager can ensure that the KPIs accurately reflect the project’s intended benefits.
upvoted 2 times
...
Wilchim
9 months, 3 weeks ago
Selected Answer: C
The correct answer is C as it is the responsibility of the business analyst to gather requirements and work with the customer to develop KPIs.
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: B
B. Coordinate with the benefit owner to track and collect the missing data and build the KPIs
upvoted 1 times
...
Bjespiritu
1 year, 2 months ago
I would go for C. It’s Business Analyst responsibility to collect the requirements right?
upvoted 1 times
...
SteAle
1 year, 3 months ago
Selected Answer: B
I would go for B as the respective business owner should be involved.
upvoted 1 times
...
Hung3102
1 year, 6 months ago
Option B is the most appropriate choice - coordinate with the benefit owner to track and collect the missing data and build the KPIs. This option involves working collaboratively with the benefit owner, who has a vested interest in tracking the project benefits. By working together, the project manager and benefit owner can identify the missing data, define the KPIs, and determine the best approach to track and report the KPIs.
upvoted 1 times
...
Sumit182
1 year, 10 months ago
B is the correct answer. Its Like saying that the scope of a product or deliverable ( KPI) is not defined , so next best step is to collect requirements from the concerned stakeholders (in this case the benefit owner)
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago