Actual exam question from PMI's PMP
Question #: 49
Topic #: 1
[All PMP Questions]

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach. This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?

  • A. Asked the sponsor to identify all required skills during the planning of the project
  • B. Identified all required skills after the kick-off of the project
  • C. Planned all required training for the team during the onboarding process
  • D. Identified all required skills during the planning of the project
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
crypto_dreams_medellin
1 week, 6 days ago
Selected Answer: D
id requirments
upvoted 1 times
...
BuviD
10 months, 3 weeks ago
Selected Answer: D
. Identified all required skills during the planning of the project
upvoted 3 times
...
Lhenica
11 months, 3 weeks ago
Selected Answer: D
Identify needed skills during planning
upvoted 1 times
...
GabMonterey
11 months, 3 weeks ago
Selected Answer: D
D is my answer
upvoted 1 times
...
Sketchie
1 year, 2 months ago
The answer is D. PM should have estimated activity resources during the planning phase.
upvoted 1 times
...
Muntadher
1 year, 4 months ago
Selected Answer: D
D from beting you have to identified all required skills during planning
upvoted 1 times
...
victory108
1 year, 6 months ago
Selected Answer: D
D. Identified all required skills during the planning of the project
upvoted 1 times
...
Anna12675
1 year, 6 months ago
Selected Answer: D
d is correct
upvoted 1 times
...
Faozi
1 year, 7 months ago
Selected Answer: D
PM is meant to hire ready skills, there is no time for training in a project. Therefore he should have planned for this earlier.
upvoted 1 times
...
shaharyarexamtopics
1 year, 8 months ago
Selected Answer: D
D is correct answer.
upvoted 1 times
...
achacyrille
1 year, 8 months ago
Selected Answer: D
This should have been handled in the planning phase of Resource Management during the Estimate Resource Process.
upvoted 1 times
...
terryp
1 year, 9 months ago
Selected Answer: D
D is correct answer.
upvoted 1 times
...
Pilot
1 year, 10 months ago
D. The keyword of this question is "What should the PM have done", what should the PM do in the first place, not what should the PM do right now
upvoted 2 times
...
PMPStudent69
1 year, 10 months ago
Selected Answer: C
C is correct. during planning process the PM don't have the resource's name so don't know if the resource have the necessary skills. the proces that involve the training is "acquire resource" (on boarding)
upvoted 1 times
PMPStudent69
1 year, 10 months ago
"Develop the team"
upvoted 1 times
...
ANAS3796
1 year, 6 months ago
The planning phase of a project is crucial for gathering requirements, defining scope, and identifying the necessary resources and skills. During this phase, the project manager should have conducted a thorough analysis to determine the technical skills required to successfully complete the deliverables.
upvoted 1 times
...
...
Ade1981
1 year, 11 months ago
D is correct
upvoted 1 times
...
Ganzee
1 year, 11 months ago
D. Identified all required skills during the planning of the project
upvoted 2 times
...
Ab5434
1 year, 11 months ago
option D is absolutely true. But it is not interesting to be in the middle of the project and emphasize that we should have paid attention to this issue in the planning phase. What should we do now? What should we do now that we are in the middle of implementing the project?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...