A project team is working on the design of a solution for a complex project. Due to a lack of clarity of the customer's requirements, daily meetings were agreed upon between the team and the customer. There are a few external contractors in the project who do not agree with this idea as they feel it is a waste of time.
What should the project manager do?
betterthanyesterday
3 days, 4 hours agoELTIGANI
6 months, 1 week agovictory108
1 year, 5 months agoSteAle
1 year, 5 months agoAlizade
1 year, 8 months agoHung3102
1 year, 8 months agoDRohan
1 year, 8 months agoWeslineo
1 year, 10 months agoleo_gold
1 year, 12 months agoSASA2030
1 year, 12 months agoleo_gold
1 year, 11 months agosuflam3
1 year, 7 months agoTomGrey
1 year, 5 months ago