A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle.
What should the project manager do in this situation?
Hashi1_snr
Highly Voted 1 year, 1 month agoZubair1
Most Recent 2 months agovlxx
2 months, 2 weeks agoYak_Yeti
1 day, 22 hours agoprklg1
3 months agoezzaariyouness
4 months, 3 weeks agonobuuu
10 months agoOnly12go
1 year, 2 months agoLucky_Cindy
1 year, 3 months agoAsakthi
1 year, 4 months agopsvexam
1 year, 4 months agoKhoiCX
7 months, 1 week agoNA1234567
5 months agoSteAle
1 year, 6 months agovictory108
1 year, 7 months agoAP2023S
1 year, 7 months agoPushkarRode
1 year, 5 months agoANAS3796
1 year, 7 months agosnagile
1 year, 8 months agoGhibliTester
1 year, 8 months agoHung3102
1 year, 9 months ago