A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.
What should the project manager do?
Sumit182
Highly Voted 1 year, 9 months agoSaintu
1 year, 9 months agoKhoiCX
4 months, 1 week agoanthonyKim
Most Recent 2 weeks, 3 days agotonybuivannghia
2 months agoDeeski
9 months, 1 week agoOnly12go
11 months, 1 week agoTuanit
11 months, 2 weeks agopsvexam
1 year, 1 month agovictory108
1 year, 3 months agoemelba
1 year, 4 months agoJYKL88
1 year, 5 months agoWeslineo
1 year, 7 months ago