Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 180 discussion

Actual exam question from PMI's PMP
Question #: 180
Topic #: 1
[All PMP Questions]

A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.
What should the project manager do?

  • A. Ask the product owner to add the missing feature in the backlog.
  • B. Invite stakeholders to discuss the impact of adding the regulatory feature.
  • C. Estimate the related cost and ask for a project extension.
  • D. Increase the capacity of the team to include the missed feature.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Sumit182
Highly Voted 1 year, 9 months ago
Its a regulatory feature , so it has to be added irrespective of the impact. . Correct option is A
upvoted 6 times
Saintu
1 year, 9 months ago
You shouldn’t just change a scope without analyzing its impact even though it is regulatory.
upvoted 4 times
KhoiCX
4 months, 1 week ago
That is the significant regulatory feature, so it is mandatory. PO needs to add to backlog first and then have a refinement meeting to discuss about the details
upvoted 1 times
...
...
...
anthonyKim
Most Recent 2 weeks, 3 days ago
B. Ask stakeholders to discuss the impact of adding regulatory features: PMBOK emphasizes that when a major change occurs, the project manager should discuss it with stakeholders and obtain approval from the change control board (CCB) or relevant authorities. If a critical regulatory feature is missing, it is important to evaluate how adding this feature will affect the scope, schedule, and cost of the project, and discuss it with stakeholders to determine adjustments to ensure successful completion of the project.
upvoted 1 times
...
tonybuivannghia
2 months ago
Selected Answer: A
PO will manage the backlog.
upvoted 1 times
...
Deeski
9 months, 1 week ago
Selected Answer: B
Stakeholders map out what the project priorities are early in the planning process so they should understand the impact of adding the regulatory feature. The Product owner owns the product backlog and should be asked to add the missing feature after discussion. That’s at least my understanding of Agile.
upvoted 2 times
...
Only12go
11 months, 1 week ago
Selected Answer: B
The best action to take when a significant feature is missing from the project backlog, especially a regulatory one, is to ensure that it is addressed and its implications understood.
upvoted 1 times
...
Tuanit
11 months, 2 weeks ago
Selected Answer: A
The feature has been missed from project backlog. PO is responsible for maintaining project backlog. So, PM must discuss with PO.
upvoted 2 times
...
psvexam
1 year, 1 month ago
Ans is A. Based on the question, looks like it is a complete miss. The team missed to add the regulatory feature. Where is the question of inviting stakeholders and having discussions to find its impact. It is evident that it is a “significant regulatory nature”. So answer is A. The PO should add it right away into backlog. Regarding if capacity is there, if it will impact schedules etc are another part of the discussion, not covered in the question. So answer is A.
upvoted 1 times
...
victory108
1 year, 3 months ago
Selected Answer: B
B. Invite stakeholders to discuss the impact of adding the regulatory feature
upvoted 1 times
...
emelba
1 year, 4 months ago
Selected Answer: B
B. Option A, asking the product owner to add the missing feature to the backlog, is not sufficient on its own because it does not address the need to assess the impact and consequences of adding the feature. option B is the most appropriate action, as it involves stakeholders in a discussion to evaluate the impact of adding the regulatory feature and enables the project manager to make an informed decision based on the insights and perspectives of relevant parties.
upvoted 1 times
...
JYKL88
1 year, 5 months ago
Option B is the answer
upvoted 1 times
...
Weslineo
1 year, 7 months ago
The.product owner might not have added it for a reason so there should be a discussion about it with stakeholders
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...