A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.
What should the project manager do?
Sumit182
Highly Voted 1 year, 11 months agoSaintu
1 year, 11 months agoKhoiCX
6 months, 1 week ago6114c29
Most Recent 1 month agoRehhakles
1 month, 1 week agoanthonyKim
2 months, 3 weeks agotonybuivannghia
4 months, 1 week agoDeeski
11 months, 1 week agoOnly12go
1 year, 1 month agoTuanit
1 year, 1 month agopsvexam
1 year, 3 months agovictory108
1 year, 5 months agoemelba
1 year, 6 months agoJYKL88
1 year, 7 months agoWeslineo
1 year, 10 months ago