A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.
What two things should the project manager do? (Choose two.)
RevZig67
Highly Voted 2 years ago462729f
Most Recent 1 month, 2 weeks agoKim222
7 months, 2 weeks agod482858
11 months, 4 weeks agoKennyMuffins
1 year, 1 month agoloscoe
1 year, 4 months agoxcjxcj
1 year, 3 months agoOnly12go
1 year, 5 months agovictory108
1 year, 6 months agoAstridN
1 year, 9 months agoDawn6699
1 year, 10 months agoHung3102
2 years agoPaulPMP
2 years agoPMPStudent
2 years, 4 months agoPMPStudent
2 years, 4 months ago