Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 685 discussion

Actual exam question from PMI's PMP
Question #: 685
Topic #: 1
[All PMP Questions]

A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.

What two things should the project manager do? (Choose two.)

  • A. Discuss the issue with the external supplier's authority.
  • B. Gather additional information and estimate the impact.
  • C. Wait for the client to raise a concern and collect more information.
  • D. Review the lessons learned from similar past projects.
  • E. Update the risk log and bring this up in the meeting with the client.
Show Suggested Answer Hide Answer
Suggested Answer: BE 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
RevZig67
Highly Voted 1 year, 5 months ago
Selected Answer: BE
The project manager should gather additional information to estimate the impact of the delay on the project's schedule and budget. Once the impact is known, the project manager should update the risk log and bring it up in the meeting with the client to discuss potential solutions and strategies to mitigate the risks associated with the delay. Discussing the issue with the external supplier's authority may be necessary, but it is not one of the immediate steps that the project manager should take. Waiting for the client to raise a concern is not proactive, and reviewing past lessons learned may not be relevant to the current situation.
upvoted 6 times
...
Kim222
Most Recent 2 weeks, 6 days ago
Selected Answer: AB
This is AB
upvoted 1 times
...
d482858
4 months, 4 weeks ago
AB. Delay is not a risk but an issue. Once it is an issue, it can’t be updated in a risk register but rather an issue log.
upvoted 1 times
...
KennyMuffins
7 months ago
Selected Answer: AB
Delay has already happened, hence it should be considered as a issue. With it being considered as an issue, the best immediate 2 steps would be A and B. Option A addresses immediate communication and resolution with the external supplier, while option B focuses on gathering information to understand the impact of the delay.
upvoted 4 times
...
loscoe
9 months, 3 weeks ago
Selected Answer: AB
E is not correct - the delay is an actual issue, no longer a risk.
upvoted 4 times
xcjxcj
8 months, 2 weeks ago
Risk become issue, you still need to update risk log, stating when it actualized.
upvoted 1 times
...
...
Only12go
11 months ago
Selected Answer: BE
B. Gathering additional information and estimating the impact (option B) is essential to understand the extent of the delay and its potential consequences on the project schedule, budget, and scope. This information will be valuable when discussing the issue with the client. E. Updating the risk log and bringing up the issue in the meeting with the client (option E) is crucial for transparency and communication. By documenting the observed delay and discussing it with the client, the project manager ensures that all stakeholders are aware of the potential risk and can collectively explore mitigation strategies or alternative approaches to minimize its impact.
upvoted 2 times
...
victory108
11 months, 3 weeks ago
Selected Answer: BE
B. Gather additional information and estimate the impact E. Update the risk log and bring this up in the meeting with the client
upvoted 2 times
...
AstridN
1 year, 2 months ago
Selected Answer: BE
I need to know more and I should share it
upvoted 2 times
...
Dawn6699
1 year, 3 months ago
Selected Answer: AB
I choose AB coz this is an issue but not risk
upvoted 2 times
...
Hung3102
1 year, 5 months ago
I will choose B and E
upvoted 3 times
...
PaulPMP
1 year, 6 months ago
A and B , this is not a risk as it already occurred but an issue.
upvoted 1 times
...
PMPStudent
1 year, 9 months ago
Selected Answer: AB
I think it is A & B. A & B are the only options that will help you with gathering details about the issue and the impact.
upvoted 2 times
...
PMPStudent
1 year, 9 months ago
Selected Answer: BD
The correct answer is B and D. It cannot be E, because the risk has already occurred. It should be logged in the issue log and not the risk register.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...