A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.
What two things should the project manager do? (Choose two.)
RevZig67
Highly Voted 1 year, 5 months agoKim222
Most Recent 2 weeks, 6 days agod482858
4 months, 4 weeks agoKennyMuffins
7 months agoloscoe
9 months, 3 weeks agoxcjxcj
8 months, 2 weeks agoOnly12go
11 months agovictory108
11 months, 3 weeks agoAstridN
1 year, 2 months agoDawn6699
1 year, 3 months agoHung3102
1 year, 5 months agoPaulPMP
1 year, 6 months agoPMPStudent
1 year, 9 months agoPMPStudent
1 year, 9 months ago