During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment.
What type of analysis should the project lead have conducted to avoid this situation?
Agratsant
1 month, 2 weeks agoWWu
2 months, 2 weeks agoWakeupsid
3 months, 1 week agokrispara
3 months, 2 weeks agojoetanant
4 months, 4 weeks agoMartinussantika
10 months, 2 weeks agoelrexyeoh
12 months agoBruce_Liu
1 year, 3 months agojosephsafiran
1 year, 3 months agovatsan1980
1 year, 4 months ago[Removed]
1 year, 5 months agoLucky_Cindy
1 year, 5 months agoChezQW
1 year, 5 months agoOnly12go
1 year, 6 months agojon0729
1 year, 6 months agoadingmaki
1 year, 6 months agovictory108
1 year, 8 months ago