During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level.
What should the project manager do next with this opportunity?
ezzaariyouness
1 month, 1 week agoKim222
1 month, 1 week agoKim222
3 weeks agotonybuivannghia
2 months agoLNX_RM_Admin
3 months, 3 weeks agoMusaad
8 months agoLucky_Cindy
10 months, 3 weeks agokevzzz
11 months, 1 week agoFyrus
11 months, 1 week agoadingmaki
11 months, 2 weeks agovictory108
1 year agoAsakthi
1 year, 1 month agoAish_
1 year, 1 month agoGinniSingh
1 year, 2 months agooshoo
1 year, 3 months agoTBT_1
1 year, 3 months agoDawn6699
1 year, 4 months agoRevZig67
1 year, 5 months agoaqz_111
1 year, 3 months ago