During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level.
What should the project manager do next with this opportunity?
e0cb955
2 months agoductrinh
3 months, 2 weeks agowittycroc
4 months, 1 week agoAgratsant
4 months, 2 weeks agovlxx
7 months, 3 weeks agoezzaariyouness
11 months, 1 week agoKim222
11 months, 1 week agoKim222
10 months, 2 weeks agotonybuivannghia
12 months agoductrinh
3 months, 2 weeks agoLNX_RM_Admin
1 year, 1 month agoMusaad
1 year, 5 months agoLucky_Cindy
1 year, 8 months agokevzzz
1 year, 9 months agoFyrus
1 year, 9 months agoadingmaki
1 year, 9 months agovictory108
1 year, 10 months agoAsakthi
1 year, 11 months agoAish_
1 year, 11 months ago