During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level.
What should the project manager do next with this opportunity?
vlxx
1 month agoezzaariyouness
4 months, 2 weeks agoKim222
4 months, 2 weeks agoKim222
3 months, 3 weeks agotonybuivannghia
5 months, 1 week agoLNX_RM_Admin
7 months agoMusaad
11 months, 1 week agoLucky_Cindy
1 year, 1 month agokevzzz
1 year, 2 months agoFyrus
1 year, 2 months agoadingmaki
1 year, 2 months agovictory108
1 year, 4 months agoAsakthi
1 year, 4 months agoAish_
1 year, 4 months agoGinniSingh
1 year, 5 months agooshoo
1 year, 6 months agoTBT_1
1 year, 6 months agoDawn6699
1 year, 7 months ago