During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level.
What should the project manager do next with this opportunity?
e0cb955
1 month, 3 weeks agoductrinh
3 months agowittycroc
4 months agoAgratsant
4 months, 1 week agovlxx
7 months, 2 weeks agoezzaariyouness
11 months agoKim222
11 months agoKim222
10 months, 1 week agotonybuivannghia
11 months, 3 weeks agoductrinh
3 months agoLNX_RM_Admin
1 year, 1 month agoMusaad
1 year, 5 months agoLucky_Cindy
1 year, 8 months agokevzzz
1 year, 8 months agoFyrus
1 year, 8 months agoadingmaki
1 year, 8 months agovictory108
1 year, 10 months agoAsakthi
1 year, 10 months agoAish_
1 year, 10 months ago