A project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones specified within the project charter.
What should the project manager do?
462729f
1 day, 11 hours agovlxx
1 month, 3 weeks agoronakxaxis
3 months, 3 weeks ago[Removed]
8 months, 3 weeks agoBruce_Liu
12 months agoUppersquareCapital
1 year, 1 month agoOnly12go
1 year, 4 months agovictory108
1 year, 5 months agokevzzz
1 year, 6 months agokevindebruyne
1 year, 6 months agoaqz_111
1 year, 8 months agokayyaly
1 year, 5 months agoAlekhyaT
1 year, 8 months agoAlekhyaT
1 year, 8 months agoHung3102
1 year, 10 months agomrbottomwood
1 year, 11 months agoMIMINEDZ
1 year, 11 months agoAstridN
1 year, 7 months agorajeshtk
1 year, 11 months ago