A project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones specified within the project charter.
What should the project manager do?
Anne99
2 weeks, 3 days agoAnne99
2 weeks, 3 days ago462729f
2 months agovlxx
3 months, 4 weeks agoronakxaxis
5 months, 4 weeks ago[Removed]
10 months, 3 weeks agoBruce_Liu
1 year, 1 month agoUppersquareCapital
1 year, 3 months agoOnly12go
1 year, 6 months agovictory108
1 year, 7 months agokevzzz
1 year, 8 months agokevindebruyne
1 year, 8 months agoaqz_111
1 year, 10 months agokayyaly
1 year, 7 months agoAlekhyaT
1 year, 10 months agoAlekhyaT
1 year, 10 months agoHung3102
2 years agomrbottomwood
2 years ago