A project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones specified within the project charter.
What should the project manager do?
ronaldjason413
6 days, 3 hours ago21d5982
1 month, 2 weeks agoe0cb955
1 month, 2 weeks agojazzuuu
1 month, 2 weeks agoAnne99
2 months, 4 weeks agoAnne99
2 months, 4 weeks ago462729f
4 months, 2 weeks agovlxx
6 months, 1 week agoronakxaxis
8 months, 1 week agoBruce_Liu
1 year, 4 months agoUppersquareCapital
1 year, 5 months agoOnly12go
1 year, 8 months agovictory108
1 year, 10 months agokevzzz
1 year, 10 months agokevindebruyne
1 year, 11 months agoaqz_111
2 years agokayyaly
1 year, 10 months agoAlekhyaT
2 years ago