Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 451 discussion

Actual exam question from PMI's PMP
Question #: 451
Topic #: 1
[All PMP Questions]

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders. The project manager has been assigned and is now in the project planning phase.
What item(s) should the project manager develop first?

  • A. A product backlog and identification of the features to be delivered
  • B. A business case and scope document
  • C. A communications management plan that addresses the team's needs
  • D. A risk management plan to incorporate known risks
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
HoangCongAnh
Highly Voted 1 year, 5 months ago
Selected Answer: C
Why not A? - Product backlog is PO responsibility Why not B? - Business case is created in Initiating phase, not in the Planning phase. Hence, Business case is already created and it is not what PM should develop first in Planning phase Why not D? You have to create Risk Management Plan then you can be able to process next step, which is Identify Risk. Therefore, you cannot develop RMP with "known" risk, this stated that you already identified the risks and you already created RMP => Answer C - develop Communication Management Plan
upvoted 20 times
SteAle
1 year, 2 months ago
Risks Mgmt process comes after Comm Mgmt Plan process according to PMBOK
upvoted 1 times
...
Hung1
1 year, 5 months ago
While the business case is typically created in the pre-project or feasibility phase, it is still an essential document that guides the project's objectives and provides justification for the project. The scope document is an important project planning document that outlines the boundaries of the project and defines what is included and excluded from the project.
upvoted 1 times
...
aqz_111
1 year, 3 months ago
yes, the PM was assigned to the project so he has authorised and the project charter has approved for the existence. It is in the initial stage, the next step after the approval of project charter is identified stakeholder, develop stakeholder register and stakeholder analysis and engagement plan. Communication and engagement are hand in hand so it is required to develop communication management plan based on the expectation of stakeholder. therefore, C is the answer
upvoted 2 times
...
...
Kim222
Most Recent 3 weeks ago
Selected Answer: C
C is alright
upvoted 1 times
...
Paramak
1 month ago
Selected Answer: B
the communications management plan should be developed after the scope and objectives are clearly defined. This ensures that communications are aligned with the project’s goals.
upvoted 1 times
...
c8ee0e6
2 months, 1 week ago
Selected Answer: B
In the project planning phase, it's essential to establish a clear foundation for the project. Developing a business case and scope document first provides the project manager with a solid understanding of: 1. Project objectives and justification (business case) 2. What needs to be delivered (scope) This will enable the project manager to: - Define the project's objectives, goals, and key performance indicators (KPIs) - Identify the key stakeholders and their requirements - Develop a clear scope statement that outlines what is included and excluded - Establish a basis for future project planning and decision-making
upvoted 2 times
...
Bruce_Liu
7 months, 4 weeks ago
Selected Answer: C
B should not have business case since it'll be provided by project sponsor during project initiating phase. And this question is highlighting cross function stakeholders, to address this context, better choose C.
upvoted 1 times
...
josephsafiran
8 months, 1 week ago
Selected Answer: B
The project manager should choose option B: A business case and scope document. At the beginning of a project, it’s crucial to establish a clear understanding of the project’s purpose and what it aims to achieve. This is typically documented in a business case. The scope document, on the other hand, outlines what will be included in the project and what will not. It sets the boundaries for the project and helps prevent scope creep. These two documents provide a solid foundation for all subsequent project planning activities.
upvoted 2 times
segatarasov
6 months, 3 weeks ago
no way, the question is about planning phase, while a business case refers to initiating
upvoted 1 times
...
...
cb4a6c4
9 months ago
Selected Answer: C
A business case is created in the initiating phase. So C would be the right choice.
upvoted 1 times
...
Psadon
9 months, 1 week ago
Selected Answer: B
In the project planning phase for a multi-year initiative with cross-functional stakeholders, the most important item for the project manager to develop first is: B. A business case and scope document. Here's why: Alignment and buy-in: The business case clearly defines the project's purpose, value, cost, and benefits, securing buy-in from key stakeholders and ensuring the project aligns with strategic goals. Scope clarity: The scope document outlines the project's boundaries, what's included and excluded, and what deliverables will be produced. This is crucial for managing expectations and preventing scope creep. Foundation for planning: The business case and scope document set the stage for other key project aspects, like the communications plan, risk management plan, and product backlog.
upvoted 1 times
...
odylec
9 months, 1 week ago
Selected Answer: B
first B and after C. You must have scope before define the communication plan
upvoted 1 times
...
[Removed]
10 months, 1 week ago
Selected Answer: B
business case and scope may have input to the communication management plan.
upvoted 1 times
...
AmitBI
1 year ago
Selected Answer: C
The project manager should first develop a communication management plan (CMP). This is because the project involves a lot of cross-functional stakeholders, and it is important to ensure that everyone is on the same page and that communication is clear and timely. The CMP should include information on the following: The project's goals and objectives The project's timeline and budget The project's stakeholders and their roles and responsibilities The methods of communication that will be used The frequency of communication The process for managing change
upvoted 1 times
...
victory108
1 year ago
Selected Answer: B
B. A business case and scope document
upvoted 1 times
...
Jamrock
1 year, 1 month ago
Selected Answer: C
This is a trick question. It has to be C. It tries to trick you with B. A business case and scope document: The business case is indeed associated with the initiating phase, as it justifies the project's existence and aligns it with the organization's strategic goals. Scope definition falls within the project planning phase, so this choice is not the most appropriate for the first item to develop during project planning.
upvoted 2 times
...
TONYJAVI
1 year, 1 month ago
Selected Answer: C
Should be C. A Communication Plan as the business case is developed in the Initiating phase of the project
upvoted 1 times
...
kevzzz
1 year, 2 months ago
Selected Answer: C
During the Planning Phase, the project team finalizes the Work Breakdown Structure, Project Plan, Requirements List, Communications Management Plan, and other relevant documents to iron out the workflow and coordination with involved parties.
upvoted 1 times
...
cwilson91
1 year, 3 months ago
Selected Answer: B
While the other options (A, C, and D) are important and will be developed during the project planning phase, the business case and scope document (B) serve as foundational elements that provide the project manager with a clear understanding of the project's purpose, objectives, and boundaries.
upvoted 1 times
...
abdelilahfa
1 year, 3 months ago
Selected Answer: B
in planning Scope is before communication plan
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...