A project team created user stories after understanding the customer requirements. As the project progresses, the project manager observes that there are too many change requests. The team feels that the outcomes they are working on are not aligned with the customer requirements.
What should the project manager do?
YOLO28
Highly Voted 1 year, 2 months agoELTIGANI
Most Recent 2 weeks, 3 days agojosephsafiran
5 months, 2 weeks agoLucky_Cindy
8 months agoOnly12go
8 months ago1234abcdefgh
9 months, 1 week agoAsakthi
10 months, 1 week agoDodoTommy
11 months agovictory108
11 months, 1 week agoSteAle
11 months, 3 weeks agoSteAle
11 months, 3 weeks agoAlekhyaT
1 year agoJMCCRAY
1 year, 1 month agowzjh2008
1 year, 3 months agoBronco30A
1 year, 5 months agoarnibert
1 year, 6 months ago