Exam PMP topic 1 question 227 discussion

Actual exam question from PMI's PMP
Question #: 227
Topic #: 1
[All PMP Questions]

A project manager is working on multiple building construction projects using a predictive project management approach. Senior leadership within the organization is promoting the inclusion of more agile practices into the current project methodologies. The project sponsor now wants the projects to use more agile methodologies.
Before mandating any agile methods to be used in a project, what should the project manager do first?

  • A. Provide agile training to those who will be part of the project team.
  • B. Shift all existing projects to agile methodologies with a strict timeline.
  • C. Pause the current projects to align them to the new agile cadence.
  • D. Assess the organizational culture and readiness for the transformation.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
TheAWSGuru
Highly Voted 1 year, 6 months ago
Selected Answer: D
D is the answer . Training would not make sense till the organization's culture is not aligned to agile wat of working .
upvoted 8 times
...
arnibert
Highly Voted 1 year, 6 months ago
Selected Answer: A
As a PM the assessment of the organizational culture and readiness for the transformation seems a bit over the top, no? Even if the PM was capable of doing so how would it affect his task? In this question the PM is requested to shift the methodology to a more agile approach so answer (A) where people get some training first would make more sense to me since it has an effect on the sponsor's request.
upvoted 5 times
...
ELTIGANI
Most Recent 2 weeks, 3 days ago
Selected Answer: D
D. Assess the organizational culture and readiness for the transformation. Before making any changes to the project management approach, it is crucial to understand the organization's culture, its readiness for adopting agile practices, and any potential resistance or challenges that might arise. This assessment will help in planning a more effective and smooth transition, ensuring that any implementation of agile methodologies is successful and well-received by the team and stakeholders.
upvoted 1 times
...
josephsafiran
5 months, 2 weeks ago
Selected Answer: D
The project manager should **D. Assess the organizational culture and readiness for the transformation**. Before implementing any significant changes, such as a shift to agile methodologies, it's crucial to understand the organization's readiness for change. This includes assessing the current culture, processes, team capabilities, and other factors that could impact the successful adoption of agile practices. This assessment will help identify potential challenges and plan appropriate strategies to address them, ensuring a smooth transition.
upvoted 1 times
...
David983
8 months ago
Selected Answer: D
D. Assess the organizational culture and readiness for the transformation.
upvoted 1 times
...
Lucky_Cindy
8 months ago
Selected Answer: D
D is correct
upvoted 1 times
...
Only12go
8 months ago
Selected Answer: D
D. Assess the organizational culture and readiness for the transformation. Before mandating the use of agile methodologies in projects, it's essential to understand the organization's current culture, its readiness for change, and the potential challenges or barriers to adopting agile practices.
upvoted 1 times
...
bu02951
8 months, 1 week ago
Selected Answer: A
The "first" thing to do is assess the organizational culture and readiness for the transformation
upvoted 1 times
...
Fyrus
9 months, 1 week ago
Selected Answer: D
If you didn't train without having the support of the organization first (that includes the project team), things like managers deciding how and what the PO should prioritize in the backlog and stakeholders asking to actively participate in daily meetings will happen. high-level people as directors may also not understand that the team must be self-organized and want to force their management ideas on the project Once the organization is aware of what agile is and the benefits of working in that way, then you can proceed with the training
upvoted 1 times
...
Asakthi
10 months, 1 week ago
D. Assess the organizational culture and readiness for the transformation.
upvoted 1 times
...
victory108
11 months, 1 week ago
Selected Answer: D
D. Assess the organizational culture and readiness for the transformation
upvoted 1 times
...
SteAle
11 months, 3 weeks ago
Selected Answer: D
D. Assess the organizational culture and readiness for the transformation.
upvoted 1 times
...
Hung3102
1 year, 2 months ago
I agree with D
upvoted 3 times
...
rmdebbie
1 year, 6 months ago
A makes more sense. If senior leadership has asked for Agile, its with the need for change to Agile. Not sure why should the PM assess org culture?
upvoted 3 times
PaulPMP
1 year, 2 months ago
You got it.That exactly I was thinking it should be a sponsor or the product owner
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago