Exam PMP topic 1 question 724 discussion

Actual exam question from PMI's PMP
Question #: 724
Topic #: 1
[All PMP Questions]

A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.

Which estimation technique should the project manager implement in this context?

  • A. Definitive estimate
  • B. Order of magnitude
  • C. Budget estimate
  • D. Story points
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Hung3102
Highly Voted 2 years ago
Order of magnitude estimation is a technique used for rough, high-level estimation, usually in the early stages of a project, when details about the project are limited. It is a quick and straightforward method to provide a rough idea of the project's overall cost or effort. In this case, the project manager needs to submit the project for urgent funding approval. Therefore, the project manager needs to provide an estimation of the project cost to request the necessary funds. Since the project is vital to the organization, the project manager needs to ensure that the estimation is reasonable and takes into account any risks that may impact the cost. The Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget. Therefore, the team's experience and past performance can be used to provide a rough estimate using the order of magnitude estimation technique. The team can use their expertise and knowledge to provide a rough estimate of the overall cost of the project.
upvoted 18 times
Hung3102
2 years ago
Definitive estimates are detailed estimates that are typically done later in the project life cycle when more information is available. Budget estimates are usually high-level estimates done for financial planning purposes. Story points are used in Agile projects to estimate the relative size of a task or a user story. These techniques are not suitable for providing a rough, high-level estimation for a new project with limited details.
upvoted 2 times
...
...
Suldan
Most Recent 1 day, 16 hours ago
Selected Answer: C
a budget estimate
upvoted 1 times
...
walkerboh
10 months ago
Selected Answer: B
Order of magnitude is needed for urgent funding approval.
upvoted 1 times
...
UA_86
10 months, 2 weeks ago
Selected Answer: B
It should be Order to magnitude estimation.
upvoted 2 times
...
Aditech
1 year ago
In the context of an urgent project vital to the organization, where the Scrum team has a strong track record of successful project deliveries and familiarity with the technology, story points estimation would provide a quick and effective way to estimate the effort required. It leverages the team's collective knowledge and experience to estimate the size and complexity of the work involved, allowing for a more accurate assessment of the project's scope and timeline. Additionally, story points estimation aligns well with Agile principles and practices, making it a suitable choice for Agile teams like the one described.
upvoted 1 times
...
Aditech
1 year ago
D Apologies for the oversight. Given the urgency and importance of the project, along with the Scrum team's extensive experience, using story points estimation technique would be appropriate. Story points are a common estimation technique in Agile projects and would allow the team to quickly estimate the effort required for completing the project based on their collective understanding and familiarity with the technology. Adigun.
upvoted 1 times
...
josephsafiran
1 year, 1 month ago
Selected Answer: D
Given the context that the Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget, it would be beneficial to use Story Points (Option D) as the estimation technique. Story points are a unit of measure for expressing an estimate of the overall effort that will be required to fully implement a product backlog item or any other piece of work. This method is commonly used in agile projects and is based on the team’s past experience, which in this case is substantial. The team’s familiarity with each other’s work habits and the project domain increases the accuracy of story point estimation. It allows the team to account for the complexity of the new technology in their estimates, making it a suitable choice for this scenario.
upvoted 1 times
...
mmhawish
1 year, 2 months ago
Selected Answer: B
B. Order of magnitude
upvoted 2 times
...
Abdelmonm
1 year, 2 months ago
Selected Answer: B
In the given context, where urgent funding approval is needed, and the project involves a new technology, an order of magnitude estimate would be suitable. This type of estimation provides a high-level, rough estimate based on historical data or expert judgment. Given that the Scrum team has worked together for over 3 years on multiple projects and has a track record of delivering under budget, using an order of magnitude estimate would provide a quick and reasonably accurate estimate for the urgent funding approval.
upvoted 3 times
...
cb4a6c4
1 year, 4 months ago
Selected Answer: D
Story Points. Team has worked together over 3 years...
upvoted 2 times
...
Only12go
1 year, 6 months ago
Selected Answer: D
Given the context that the Scrum team has worked together for over 3 years on multiple projects, and the project will use a new technology, the best estimation technique would be: D. Story points. Rationale: In Agile and Scrum, story points are a common method of estimating work complexity. They allow teams to estimate work without focusing on the exact time it would take, which is particularly useful when dealing with new technologies where precise time estimation can be challenging.
upvoted 3 times
...
victory108
1 year, 6 months ago
Selected Answer: D
D. Story points
upvoted 2 times
ChezQW
1 year, 6 months ago
Story points are used to estimate the effort needed to complete a task not the cost. Additionally, this is a new piece of software so the team may not be able to estimate the costing accurately beyond a 25% to 75% range, therefore the answer is B.
upvoted 5 times
...
...
emelba
1 year, 11 months ago
Selected Answer: B
option B is correct, since Story Points (option D) are typically used for estimating the effort required to complete user stories, not for determining project costs and timelines.
upvoted 4 times
...
kevzzz
1 year, 11 months ago
Selected Answer: B
Rough order of magnitude (ROM) refers to an initial estimate of the cost of a project or parts of a project. It has an expected accuracy of -25% to +75% according to the PMBOK (other sources suggest -50% to +50%). In other words, the actual costs of a project are typically expected to be between 75% and 175% (or 50% to 150%) of the ROM estimate.
upvoted 4 times
...
Kukusha
2 years, 1 month ago
The facts that the team is a SCRUM and that the involvement of new technology imply that there is uncertainty in scope and hence budget cannot be a definite one. Besides there is urgency for budget approval. Thus, for me ROM is the best answer
upvoted 1 times
...
mrbottomwood
2 years, 1 month ago
Option B, Rough Order of Magnitude (ROM) estimate is also a valid estimation technique when there is an urgent need for funding approval. However, ROM estimates are typically used when there is a high level of uncertainty about project requirements, scope, and objectives. In this scenario, it is mentioned that the project is vital to the organization and the entire Scrum team has worked together for over 3 years on multiple projects. This suggests that there is a higher level of certainty regarding the project requirements, scope, and objectives, and a budget estimate would be more appropriate in this context.
upvoted 2 times
mrbottomwood
2 years, 1 month ago
Budget estimates are typically used to provide a high-level estimate of the total cost of the project, based on historical data, industry benchmarks, or expert judgment. This approach is more appropriate when there is a higher level of certainty about the project requirements, scope, and objectives. In summary, both a budget estimate and ROM estimate are valid estimation techniques, but the choice of technique will depend on the level of uncertainty surrounding the project requirements, scope, and objectives. In this scenario, a budget estimate is more appropriate given the higher level of certainty surrounding the project.
upvoted 1 times
mrbottomwood
2 years, 1 month ago
Therefore option C is my choice.
upvoted 1 times
...
...
...
Brainfreeze
2 years, 1 month ago
what is the real right answer?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago