Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 761 discussion

Actual exam question from PMI's PMP
Question #: 761
Topic #: 1
[All PMP Questions]

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months.

What should the project manager do first?

  • A. Set up a steering committee session to review the project delay.
  • B. Continue with the approved design so that the project is not delayed.
  • C. Log the technical design delay as a risk in the project risk log.
  • D. Ask the steering committee to approve a new technical design.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ea4e1f8
4 weeks, 1 day ago
Selected Answer: A
While documenting the delay is important, it should not be the first step. The priority is to address the situation collaboratively with the steering committee before logging it as a risk.
upvoted 1 times
...
Abdelmonm
7 months, 3 weeks ago
Selected Answer: C
In this situation, it's essential to promptly document the identified issue, which is the impact on the company's production system due to the approved design. Logging this delay as a risk in the project risk log allows for proper documentation, analysis, and communication of the potential delay. It provides a basis for discussions with the project steering committee and other stakeholders to determine the most appropriate course of action.
upvoted 2 times
...
AntoFE
8 months, 3 weeks ago
Selected Answer: C
I think the question was poorly phrased. Initially the focus was placed on the Technical Design that would impact the Company Production Environment. However, it says the new technical design "Could" impact the timeline and "might not happen or yet to happen" so its still a risk. The question is really about the impact on the timeline - so the better answer is C. (Although I choose A initially)
upvoted 3 times
...
odylec
9 months ago
Selected Answer: C
C is the answer
upvoted 1 times
...
[Removed]
10 months, 1 week ago
Selected Answer: A
Analysis first.
upvoted 1 times
...
Only12go
11 months ago
Selected Answer: A
Bad question: but In summary, in the context of the scenario provided, once the project manager identifies the issue and realizes its potential impact, they should set up the steering committee session (strategic action) and log the issue as a risk almost concurrently. The exact timing might depend on the specific processes and protocols of the organization, but both steps are crucial and should be executed promptly. So, while documenting the delay in the risk register is a crucial step in risk management, the immediate need in this scenario is to engage the steering committee to address the significant impact on the project timeline.
upvoted 1 times
...
adingmaki
11 months, 2 weeks ago
Selected Answer: C
PLEASE READ! A new technical design must be found and this COULD delay the project by 3 months. The technical design caused an ISSUE. That is correct. But finding a new technical COULD delay the project by 3 months. That's the risk. Register this.
upvoted 4 times
...
victory108
11 months, 3 weeks ago
Selected Answer: A
A. Set up a steering committee session to review the project delay
upvoted 1 times
...
Aish_
1 year, 1 month ago
The question says company's production will be impacted. This is an issue. The question says that project COULD be delayed which is a risk. So this delay should be logged in Risk register, which makes sense and so that should be the correct answer.
upvoted 1 times
...
cwilson91
1 year, 3 months ago
I'll stick with C. Nowhere in the question does it state the risk has already been formally logged. "Logging the delay as a risk allows the project manager to formally document the issue, assess its potential impact on the project objectives, and determine the appropriate risk response strategies. The project manager can then communicate the risk to the project stakeholders, including the project steering committee, to ensure awareness and collaboration in finding a solution. Options A, B, and D involve actions that are premature at this stage. Setting up a steering committee session to review the project delay (option A) may be necessary, but it should come after the risk is formally identified and assessed."
upvoted 2 times
...
Neil20
1 year, 3 months ago
Selected Answer: A
!a is correct
upvoted 1 times
...
noppy
1 year, 3 months ago
Selected Answer: A
I think the correct answer is A. The risks have already been identified("discovered"), and in such a situation, the first step to take is to follow the risk management plan. In this case, it would involve implementing the responses outlined in the risk management plan. According to PMI's "The Standard For Risk Management," in section 4.6 "PLAN RISK RESPONSES," it can be "Escalate" the risks. In the given scenario, there is a high likelihood that the "steering committee" would be the appropriate escalation point (as they have provided approval). Therefore, I believe A is the most likely correct answer. Additionally, when it comes to "logging" the "technical design delay" mentioned in option C, it should be done when there is still a possibility(need to rate "likelihood" in risk managment plan) of that situation occurring.
upvoted 1 times
...
VPNalumni
1 year, 5 months ago
This is a issue or a risk. A seems to be more appropriate. Risk should be uncertain.
upvoted 1 times
...
longge
1 year, 7 months ago
I am confused by C, it is Risk log, not Risk Register???
upvoted 1 times
Fanboy
1 year, 6 months ago
A risk register, sometimes known as a risk log
upvoted 1 times
...
...
15rajanikanthhotie
1 year, 9 months ago
Selected Answer: C
Yes answer C is right
upvoted 2 times
...
mjs
1 year, 9 months ago
Why not A?
upvoted 2 times
PMPStudent
1 year, 9 months ago
Because it is asking, what will you do FIRST? The first thing that the PM will do is log the risk in the risk register and then inform the stakeholders. You need to go prepared in that meeting with impact analysis and alternative solutions/mitigations, and who will be the risk owner that will continually monitor the risk.
upvoted 5 times
James10
1 year, 8 months ago
Since it says it WILL impact, isn't that an issue and not a risk?
upvoted 4 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...