A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company's production system. A new technical design must be found and this could delay the project by 3 months.
What should the project manager do first?
ea4e1f8
4 weeks, 1 day agoAbdelmonm
7 months, 3 weeks agoAntoFE
8 months, 3 weeks agoodylec
9 months ago[Removed]
10 months, 1 week agoOnly12go
11 months agoadingmaki
11 months, 2 weeks agovictory108
11 months, 3 weeks agoAish_
1 year, 1 month agocwilson91
1 year, 3 months agoNeil20
1 year, 3 months agonoppy
1 year, 3 months agoVPNalumni
1 year, 5 months agolongge
1 year, 7 months agoFanboy
1 year, 6 months ago15rajanikanthhotie
1 year, 9 months agomjs
1 year, 9 months agoPMPStudent
1 year, 9 months agoJames10
1 year, 8 months ago