Exam PMP topic 1 question 593 discussion

Actual exam question from PMI's PMP
Question #: 593
Topic #: 1
[All PMP Questions]

The project sponsor on an agile project informed the project lead that an executive would like an update on the project's progress.
What should the project lead do?

  • A. Provide a link to the project's shared drive for the executive to search through for any artifacts that are of interest
  • B. Invite the executive to the project's meeting space to determine if the project information radiators meet their needs
  • C. Reach out to the project management office (PMO) for status report templates and provide project updates in that format
  • D. Ask the project sponsor or product owner to provide an update since the project lead should be trying to keep the team free from impediments
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Kim222
3 weeks ago
Selected Answer: B
This is B
upvoted 1 times
...
DavidTri
2 months, 1 week ago
Selected Answer: B
PM should navigate executive to project information radiators to get the info which they want because all info record and store there
upvoted 1 times
...
6thEditionAndy
10 months ago
Selected Answer: B
In theory B, in practice C. If the CFO needs an update, you are not asking him to come down to your work space so he can look at a board. The CFO wants a slide that he can re-use in his own presentation.
upvoted 1 times
...
Only12go
11 months ago
Selected Answer: B
When an executive expresses interest in an update on an agile project, the project lead should ensure effective communication while minimizing disruptions to the team's work. Option B is the most appropriate course of action:
upvoted 1 times
...
victory108
1 year ago
Selected Answer: B
B. Invite the executive to the project's meeting space to determine if the project information radiators meet their needs
upvoted 1 times
...
Aish_
1 year, 1 month ago
Selected Answer: B
Option C suggests reaching out to the project management office (PMO) for status report templates and providing project updates in that format. While this could be a valid approach for status reporting in traditional project management, it may not align well with the agile approach. In agile projects, the focus is on frequent and transparent communication, and information radiators such as task boards, burndown charts, and other visual indicators are commonly used to keep the team and stakeholders updated on progress. Agile projects generally emphasize face-to-face interactions and collaborative discussions over formal reports.
upvoted 2 times
...
TONYJAVI
1 year, 1 month ago
Selected Answer: B
Option B seems way more Agile than C.
upvoted 1 times
...
SteAle
1 year, 1 month ago
Selected Answer: B
https://www.examtopics.com/discussions/pmi/view/50898-exam-pmp-topic-1-question-2553-discussion/
upvoted 2 times
...
noppy
1 year, 3 months ago
Selected Answer: C
I will go to C. There is a clear explnation of what is information radiators in PMBOK as below "Information radiator : This artifact is a visible, physical display that provides information to the rest of the organization, enabling timely knowledge sharing." I don't think executive can be considered as "the rest of the organization". I think executive is busy and has to decide many things. It means they need to shorten checking time for information. How to shorten this time? use something familiar with. that why we use report template if it exists.
upvoted 2 times
...
[Removed]
1 year, 3 months ago
Selected Answer: C
If the executive is not a part of the project team but a stakeholder then shouldn't PMO be contacted to ensure that the templates are good to communicate? Thoughts?
upvoted 3 times
...
Hung3102
1 year, 5 months ago
When an executive requests an update on an agile project, the project lead should invite them to the project's meeting space. This is because agile teams use visual information radiators to keep stakeholders informed of the project's progress. This will help the executive to see the current status of the project and understand how the team is working. Additionally, the project lead can use this opportunity to discuss any concerns or issues that the executive may have.
upvoted 4 times
...
LuanND
1 year, 7 months ago
Selected Answer: B
B correct. Page 708 PMBook 6: These metrics and projections are shared with project stakeholders via trend graphs (information radiators) to communicate progress, share issues, drive continuous improvement activities, and manage stakeholder expectations.
upvoted 1 times
...
PMPStudent
1 year, 9 months ago
Selected Answer: B
B is correct.
upvoted 1 times
...
Bobbie30
1 year, 9 months ago
Sounds more like A to me. Any thoughts?
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.