During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics:
1,600 rpm (rate-per-minute) -> stops working and crashes the system
1,500 rpm (rate-per-minute) -> warns of max rate allowed
1,400 rpm (rate-per-minute) -> reduces the power and brakes the engine
Which of the following statements is correct?
462729f
1 month, 2 weeks agoDavidTri
9 months, 1 week agoKen_JP_206
10 months, 2 weeks agoxcjxcj
1 year, 3 months agoDavid983
1 year, 5 months agoUncle_Lucifer
1 year, 5 months agoOnly12go
1 year, 6 months agovictory108
1 year, 7 months agoSteAle
1 year, 8 months agoSteAle
1 year, 8 months agoJeongjoo
1 year, 10 months agoHung1
1 year, 12 months agoRevZig67
2 years agoyuliang0903
2 years, 3 months agoBobbie30
2 years, 4 months agomrbottomwood
2 years agomrbottomwood
2 years ago