Charter is a document focused in giving authorization and identify who would be PM mostly. Risk in there are related to business, not project. The question ask for team members and identify risks which is in planning group
The answer is B. You also need in-depth risk identification sessions at specific critical points in project planning where you take a broader look at the project as a whole
Refer to PMBOK page 25 - under process group 'Planning' risk is started @ knowledge area Project Risk Management.
upvoted 2 times
...
This section is not available anymore. Please use the main Exam Page.CAPM Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
MP_2022
Highly Voted 11 months agoanfacer
10 months, 2 weeks agomeg002
Highly Voted 10 months, 3 weeks agome22
Most Recent 10 months, 3 weeks ago