Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 670 discussion

Actual exam question from PMI's PMP
Question #: 670
Topic #: 1
[All PMP Questions]

A project team is performing a post-release evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have promptly provided feedback. One of them has not provided any feedback despite numerous requests from the team.

What should the project manager do in this situation?

  • A. Explain to the sponsor why the reluctant stakeholder needs to provide feedback.
  • B. Host a meeting with the reluctant stakeholder and project team to resolve any conflict.
  • C. Meet with all seven of the project stakeholders and request all of their feedback.
  • D. Schedule a meeting with the reluctant project stakeholder to obtain their feedback.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
leo_gold
Highly Voted 1 year, 9 months ago
D makes more sense - The question didn't mention any conflict and the needed action is to get the feedback.
upvoted 8 times
...
PMPStudent
Highly Voted 1 year, 9 months ago
Selected Answer: D
D is a better option
upvoted 5 times
...
c8ee0e6
Most Recent 2 months, 1 week ago
Selected Answer: D
Since the team has already requested feedback numerous times, a more direct approach is necessary. By scheduling a meeting with the reluctant stakeholder, the project manager can: 1. Understand the reasons behind the delay in providing feedback 2. Address any concerns or issues that might be hindering their response 3. Emphasize the importance of their feedback in the evaluation process 4. Obtain the necessary feedback in a personalized setting
upvoted 1 times
...
d482858
5 months ago
Selected Answer: D
There is no mention of conflict. The best thing is to schedule a meeting.
upvoted 1 times
...
Abdelmonm
7 months, 3 weeks ago
Selected Answer: D
In this situation, the project manager should proactively schedule a meeting with the reluctant stakeholder to address any concerns, gather feedback, and ensure their input is included in the post-release evaluation. This direct communication can help uncover any issues or reasons for the delay in providing feedback and facilitate a resolution.
upvoted 1 times
...
xcjxcj
8 months, 1 week ago
Selected Answer: B
If team cannot get feedback, how can PM simply get, just by a feedback meeting one-on-one? Meeting must be with the stakeholder together with the team.
upvoted 2 times
...
odylec
9 months, 1 week ago
Selected Answer: B
B is the answer. Because you must learn why he did give his feedback
upvoted 2 times
...
David983
11 months, 2 weeks ago
Selected Answer: B
In Agile, the Project Manager is a facilitator and a servant leader who should remove obstacles to enable the team to perform at their best. Additionally, the PM is responsible for the maturity and evolution of the team. In this case, shouldn't the PM involve the team in the meeting to learn how to address issues with stakeholders and thus become more self-reliant in the future?
upvoted 2 times
David983
11 months, 1 week ago
to ratify my answer, Team members asked many times for the stakeholder feedback what can be translated into that may be there are any conflict between both parts, option B will address and clarify it.
upvoted 2 times
...
...
victory108
11 months, 4 weeks ago
Selected Answer: D
D. Schedule a meeting with the reluctant project stakeholder to obtain their feedback
upvoted 1 times
...
miggykurkova
1 year ago
Answer is B: Reluctant stakeholder should meet with the team.
upvoted 2 times
...
Aish_
1 year, 1 month ago
Selected Answer: B
Stakeholder Not providing feedback after numerous requests from the team is a conflict that should be resolved. So, its not just the matter of getting feedback from them.
upvoted 2 times
...
kevzzz
1 year, 3 months ago
Selected Answer: D
As the PM you don't want to call out the stakeholder in front of the team in a meeting. You just want to talk with the stakeholder since you may work with the stakeholder again on another project.
upvoted 3 times
...
rajeshtk
1 year, 5 months ago
The stakeholder might be busy or on leave. There is no mention of conflict. The best answer would be "D"
upvoted 1 times
...
Alizade
1 year, 5 months ago
Selected Answer: D
D. Schedule a meeting with the reluctant project stakeholder to obtain their feedback.
upvoted 1 times
...
sanjiiv
1 year, 6 months ago
Selected Answer: D
There is no mention of conflict so D is my choice
upvoted 2 times
...
Fanboy
1 year, 6 months ago
But looks like the project team is not part of it
upvoted 1 times
...
longge
1 year, 7 months ago
Selected Answer: B
I prefer to B, the stakeholder is supposed to provide feedback by numerous requests, and he did not, so there must be something he is not happy with, we need to solve it.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...