A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board
(CCB).
What should the project manager do now?
AP2023S
Highly Voted 1 year, 6 months agosegatarasov
8 months, 3 weeks agoadingmaki
Highly Voted 1 year, 1 month agoAmirov
Most Recent 3 weeks, 4 days agoKim222
3 months, 2 weeks agoLNX_RM_Admin
5 months, 3 weeks agoMartinussantika
5 months, 4 weeks agoShittu1
9 months agojosephsafiran
9 months, 2 weeks agoshawndude
9 months, 4 weeks agojosephsafiran
10 months, 2 weeks agoBruce_Liu
10 months, 3 weeks agofutbool10
11 months, 3 weeks agoprinceviper
1 year agoestimater
1 year agoUncle_Lucifer
1 year agoChezQW
1 year, 1 month agoLucky_Cindy
1 year, 1 month ago