A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board
(CCB).
What should the project manager do now?
AP2023S
Highly Voted 1 year, 7 months agosegatarasov
10 months agoadingmaki
Highly Voted 1 year, 2 months agovlxx
Most Recent 1 month agoAmirov
2 months agoKim222
4 months, 3 weeks agoLNX_RM_Admin
7 months agoMartinussantika
7 months agoShittu1
10 months, 1 week agojosephsafiran
10 months, 3 weeks agoshawndude
11 months agojosephsafiran
11 months, 3 weeks agoBruce_Liu
11 months, 4 weeks agofutbool10
1 year agoprinceviper
1 year, 1 month agoestimater
1 year, 1 month agoUncle_Lucifer
1 year, 2 months agoChezQW
1 year, 2 months ago