exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 278 discussion

Actual exam question from PMI's PMP
Question #: 278
Topic #: 1
[All PMP Questions]

A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board
(CCB).
What should the project manager do now?

  • A. Notify the project team about the change request's approval.
  • B. Include the new branch of the bridge in the design.
  • C. Communicate the decision to the stakeholder who requested the change.
  • D. Evaluate the adjustments to the project management plan.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AP2023S
Highly Voted 1 year, 7 months ago
Selected Answer: C
D is absurd: any evaluation of changes to the project (schedule, cost, plan..) is made before the change request or during the approval process. Not after...
upvoted 17 times
segatarasov
10 months ago
exactly
upvoted 1 times
...
...
adingmaki
Highly Voted 1 year, 2 months ago
Selected Answer: A
This is A. From PMBOK 6th (4.6.3.1) Approved change requests will be implemented through Direct and Manage Project Work. Deferred or rejected change requests are communicated to the person or group requesting the change. From PMI Website: https://www.projectmanagement.com/wikis/396744/change-management-process-for-project If the change is approved, the following will occur: The change will be communicated to the team Project deliverables will be updated to reflect the change The change request will be closed on the CID Log All approved change requests will be communicated in the "Project Name" status report
upvoted 14 times
...
vlxx
Most Recent 1 month ago
Selected Answer: D
D. When a major change request is approved, the next step is to evaluate its impact on the project management plan (scope, schedule, budget, quality, and other aspects).
upvoted 1 times
...
Amirov
2 months ago
Selected Answer: D
After the change request has been accepted by the Change Control Board (CCB), the project manager should take the following steps as part of the change management process according to PMI guidelines: Next Steps: Update Project Documents: Revise the project management plan, including the scope, schedule, and cost baselines, to reflect the approved changes. This includes updating any relevant project documents such as the project scope statement, WBS (Work Breakdown Structure), and schedule baseline. Communicate the Change: Inform all relevant stakeholders about the change and its implications. This includes the project team, clients, and any other parties affected by the change. Clear communication ensures that everyone understands how the change will impact the project moving forward.
upvoted 2 times
...
Kim222
4 months, 3 weeks ago
Selected Answer: A
6.4 Closing the Change Request If the change is approved, the following will occur: The change will be communicated to the team Project deliverables will be updated to reflect the change The change request will be closed on the CID Log All approved change requests will be communicated in the "Project Name" status report
upvoted 3 times
...
LNX_RM_Admin
7 months ago
Selected Answer: A
The CR was approved. D is before approval
upvoted 1 times
...
Martinussantika
7 months ago
Selected Answer: D
A and B part of D activities.
upvoted 2 times
...
Shittu1
10 months, 1 week ago
Selected Answer: D
D. Evaluate the adjustments to the project management plan. After the change request has been reviewed and accepted by the change control board (CCB), the project manager should evaluate the adjustments required to the project management plan. This includes updating the project scope, schedule, budget, and any other relevant plans to incorporate the new branch of the bridge into the engineering design. While notifying the project team (option A) and including the new branch in the design (option B) are important steps, they should be done after evaluating the adjustments to the project management plan. Similarly, communicating the decision to the stakeholder who requested the change (option C) is also important but should be done in conjunction with the other actions. The first step is to evaluate the impact of the change on the project management plan to ensure that the project remains on track and aligned with the new requirements.
upvoted 2 times
...
josephsafiran
10 months, 3 weeks ago
Selected Answer: A
the sequence of these actions may vary depending on the specific circumstances of the project. Typically, the project manager would first notify the project team (A), then update the design (B), evaluate the adjustments to the project management plan (D), and finally communicate the decision to the stakeholder
upvoted 1 times
...
shawndude
11 months ago
Selected Answer: B
This is already approved. The PM needs to execute the change by adding the new design feature.
upvoted 2 times
...
josephsafiran
11 months, 3 weeks ago
The project manager should **D. Evaluate the adjustments to the project management plan**. Now that the change request has been approved, it's important to understand how this change will impact the project's scope, schedule, cost, and other areas. The project manager will need to update the project management plan to reflect these changes. This could involve adjusting the schedule, reallocating resources, revising cost estimates, and more. Once the project management plan has been updated, the project manager can then proceed with implementing the change, which includes notifying the project team, updating the design, and communicating with stakeholders. However, the specific actions will depend on the project's change management plan and the specific circumstances of the situation.
upvoted 1 times
...
Bruce_Liu
11 months, 4 weeks ago
Selected Answer: D
D is the first thing for PM to do after CR approved.
upvoted 1 times
...
futbool10
1 year ago
#A 6.4 Closing the Change Request If the change is approved, the following will occur: 1.The change will be communicated to the team 2.Project deliverables will be updated to reflect the change 3.The change request will be closed on the CID Log 4.All approved change requests will be communicated in the "Project Name" status report
upvoted 1 times
...
princeviper
1 year, 1 month ago
Selected Answer: A
A is correct. Because the correct process is: Approve/reject by CCB > Inform relevant stakeholders > update related docs: > Update change log > Input to 4.3 (direct and manage proj. work) > Action!
upvoted 2 times
...
estimater
1 year, 1 month ago
Selected Answer: D
D. Evaluate the adjustments to the project management plan. after that deplyment the official management plan to the others
upvoted 1 times
...
Uncle_Lucifer
1 year, 2 months ago
Selected Answer: C
Team members and other people are part of stakeholders - inclusive, therefore better answer than A. --> answer is C
upvoted 2 times
...
ChezQW
1 year, 2 months ago
Selected Answer: A
I voted for A because all evaluations should be completed to complete the change requests and during the evaluation process of the change request by the CCB.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago