A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board
(CCB).
What should the project manager do now?
AP2023S
Highly Voted 1 year, 11 months agosegatarasov
1 year, 1 month agoadingmaki
Highly Voted 1 year, 6 months agoAgratsant
Most Recent 1 month, 2 weeks agoWWu
2 months, 1 week agokrispara
3 months, 2 weeks agovlxx
4 months, 3 weeks agoAmirov
5 months, 3 weeks agoKim222
8 months, 2 weeks agoLNX_RM_Admin
10 months, 3 weeks agoMartinussantika
10 months, 3 weeks agoShittu1
1 year, 1 month agojosephsafiran
1 year, 2 months agoshawndude
1 year, 2 months agojosephsafiran
1 year, 3 months agoBruce_Liu
1 year, 3 months agofutbool10
1 year, 4 months agoprinceviper
1 year, 5 months ago