A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board
(CCB).
What should the project manager do now?
AP2023S
Highly Voted 1 year, 4 months agosegatarasov
6 months, 3 weeks agoadingmaki
Highly Voted 11 months, 1 week agoKim222
Most Recent 1 month, 2 weeks agoLNX_RM_Admin
3 months, 3 weeks agoMartinussantika
3 months, 4 weeks agoShittu1
7 months agojosephsafiran
7 months, 2 weeks agoshawndude
7 months, 4 weeks agojosephsafiran
8 months, 2 weeks agoBruce_Liu
8 months, 3 weeks agofutbool10
9 months, 3 weeks agoprinceviper
10 months, 3 weeks agoestimater
10 months, 3 weeks agoUncle_Lucifer
10 months, 4 weeks agoChezQW
11 months agoLucky_Cindy
11 months agoRicholo
11 months, 1 week ago