A project has been reporting a declining schedule performance index (SPI) for the past four reviews. No corrective action is under development, and the project team does not seem concerned.
What should the project manager do first to address the SPI trend?
Alizade
Highly Voted 1 year, 6 months agoAbdelmonm
Most Recent 8 months, 3 weeks agochlaithem
9 months, 2 weeks agoAgmaze
10 months, 2 weeks agoSumbo
1 year agovictory108
1 year agoslick90
1 year, 3 months agoRobin0229
1 year, 3 months agoNemona1979
1 year agosanjiiv
1 year, 7 months agoCert_IT
1 year, 9 months agoPMPStudent
1 year, 10 months agopoohwinniewong
1 year, 10 months agomjs
1 year, 10 months agoaqz_111
1 year, 3 months agoBobbie30
1 year, 10 months ago