Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 100 discussion

Actual exam question from PMI's PMP
Question #: 100
Topic #: 1
[All PMP Questions]

A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change requests issued due to the nature of the project.
What should the project manager do?

  • A. Reduce the number of approvers required to implement a change request
  • B. Request sponsor approval for all change requests to reduce the number of changes
  • C. Initiate the number of iterations to reduce the number of change requests
  • D. Add a fixed number of change requests allowed by the client on the project baseline
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Annetarsi
Highly Voted 1 year, 1 month ago
An iterative approach makes sense, so understand the rationale, but "initiate the number of iterations" makes no sense. What does that mean? It's either bad sentence structure or just misleading on purpose.
upvoted 8 times
...
QuaTV
Most Recent 2 weeks ago
Selected Answer: C
"Initiating iterative cycles to reduce change requests" means starting multiple rounds of evaluation and continuous improvement to ensure that the product or project meets the requirements from the outset. This approach minimizes the need for change requests later on, helping the project proceed more smoothly while reducing potential costs and delays.
upvoted 1 times
...
Davard
8 months ago
Selected Answer: C
Weird wording, but the use of iterative development allows for continuous feedback and adjustments throughout the project. By breaking the project into iterations, the project manager can incorporate changes more smoothly and efficiently, reducing the need for a large number of change requests. Option A suggests reducing the number of approvers, which might not address the root cause of the challenges. Option B proposes requiring sponsor approval for all change requests, which might slow down the project and hinder its adaptability to uncertainties. Option D involves adding a fixed number of change requests to the project baseline, which may not be suitable for innovation projects with high uncertainty.
upvoted 4 times
...
alool2
10 months, 2 weeks ago
And they're like, ", Agile is so flexible!"
upvoted 1 times
...
Only12go
11 months, 1 week ago
Selected Answer: C
Looks like C is the anwser but the wording is bad. D is plausible as well but placing limits can be problematic.
upvoted 1 times
...
McFaceplant
11 months, 1 week ago
"Initiate the number of iterations" -WTF does this even mean?
upvoted 4 times
...
Tracyyy123
11 months, 1 week ago
Selected Answer: D
All answers sound wrong, but I feel like D is the best
upvoted 4 times
...
Lucky_Cindy
1 year ago
C, "Initiate the number of iterations to reduce the number of change requests."
upvoted 1 times
...
Asakthi
1 year, 1 month ago
Option c is the only correct
upvoted 1 times
...
bug_bloke
1 year, 1 month ago
Selected Answer: C
C, "Initiate the number of iterations to reduce the number of change requests." Innovation projects often involve a high level of uncertainty, and it can be challenging to accurately define all requirements and details upfront. In such cases, the project manager can adopt an iterative approach to manage the project effectively. By breaking the project into smaller, manageable iterations, the team can focus on delivering incremental results while continuously learning and adapting based on feedback and changing requirements. Through iterations, the project team can gather valuable insights, test assumptions, and refine the project's direction. This can potentially lead to a reduction in the number of change requests over time as the project evolves based on the gained knowledge and experience.
upvoted 1 times
...
victory108
1 year, 4 months ago
Selected Answer: C
C. Initiate the number of iterations to reduce the number of change requests
upvoted 1 times
...
Mobarak7
1 year, 5 months ago
Selected Answer: C
I vote for C
upvoted 1 times
...
Sarish07
1 year, 6 months ago
The best answer is C..
upvoted 1 times
...
Hung3102
1 year, 6 months ago
Choose C. You can mixed C and D, apply a fixed number of CR in each iteration.
upvoted 1 times
...
Najlaaabbas
1 year, 6 months ago
In my opinion, the project manager cannot limit the change requests because that could go against the product value, however, the PM can control the behavior that lead to random changes.
upvoted 1 times
...
Red_Apple1
1 year, 6 months ago
Selected Answer: A
Why C??
upvoted 1 times
Jamrock
1 year, 2 months ago
loL. WHY A.? no mentioned that the approval process is the issue. in fact it is clear the issue is the projects are unclear and CRs are high.
upvoted 1 times
...
...
Trytrio
1 year, 6 months ago
Selected Answer: D
Somehow D sounds plausible to me. If somebody is randomly throwing requests in you should limit them to really only get the prioritized change requests but maybe I am wrong here. Answer C I don't understand in regards to the wording "Initiating the number of iterations" ...what does that even mean
upvoted 2 times
Jamrock
1 year, 2 months ago
limiting change requests is never the answer. assumption is a change request is simply the creation of documenting a need. can have them created as many times needed. But how many get approved based on timelines that is a different story and not what the option is saying. initiating means dictating what will the point we release the products/solution. so how many. they could have said t that way i suppose.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...