A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects, and there is no capacity for any developer to take on additional work.
What should the project manager do next to fulfill this resource need?
ELTIGANI
4 months, 3 weeks agomesacgon
11 months, 3 weeks agoLucky_Cindy
1 year agovictory108
1 year, 3 months agoSteAle
1 year, 3 months agoaqz_111
1 year, 5 months agoJamrock
1 year, 3 months agoAlizade
1 year, 6 months agoarnibert
1 year, 10 months agoJamrock
1 year, 3 months agoleo_gold
1 year, 10 months agoRainyLe
1 year, 11 months agoJamrock
1 year, 3 months ago