A project is ready to start, and resources are allocated. The development manager then informs the project manager that a critical resource is no longer available due to a family emergency. The development manager indicates that all other developers have been assigned to other projects, and there is no capacity for any developer to take on additional work.
What should the project manager do next to fulfill this resource need?
ELTIGANI
2 weeks, 3 days agomesacgon
7 months, 2 weeks agoLucky_Cindy
8 months agovictory108
11 months, 1 week agoSteAle
11 months, 3 weeks agoaqz_111
1 year, 1 month agoJamrock
11 months, 2 weeks agoAlizade
1 year, 2 months agoarnibert
1 year, 6 months agoJamrock
11 months, 2 weeks agoleo_gold
1 year, 6 months agoRainyLe
1 year, 6 months agoJamrock
11 months, 2 weeks ago