A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.
Which measure should mitigate the impact of this key resource's departure?

  • A. Establish a proactive knowledge-sharing plan
  • B. Offer a new contract to the resource who is leaving
  • C. Develop a contingency budget to replace the key resource
  • D. Update the risk register and inform the customer
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Selected Answer: A
D. Update the risk register and inform the customer - Notifying the customer may raise unnecessary concerns.
upvoted 1 times
...
Dami77
9 months ago
Selected Answer: A
While D is a very good option, the question was specific about "mitigating the impact" risk register updates will not in itself mitigate the impact but knowledge sharing is a direct mitigating factor against losing a key resource
upvoted 2 times
...
Asakthi
1 year, 3 months ago
D, update the risk register since is he is critical resource
upvoted 1 times
Davonos
1 year, 3 months ago
I agree with you. Knowledge sharing is good, but might not be sufficient seeing that a gap will be created and no team may be able to fill in
upvoted 1 times
...
...
SteAle
1 year, 4 months ago
Selected Answer: A
Answer A. here, the question is about a specific mitigation actions.
upvoted 2 times
...
emelba
1 year, 6 months ago
Selected Answer: D
D. The normal thing in the day to day of a perfect project manager is to share knowledge, for that it is not necessary to study the PMP. I vote to update the risk register, as the documents are ridiculously sacred to PMI.
upvoted 3 times
...
victory108
1 year, 6 months ago
Selected Answer: A
A. Establish a proactive knowledge-sharing plan
upvoted 1 times
...
Ganzee
1 year, 11 months ago
A. Establish a proactive knowledge-sharing plan
upvoted 1 times
...
PMPStudent
1 year, 11 months ago
Selected Answer: A
A is the correct answer. Adding to the risk register and informing the client will not reduce the impact.
upvoted 2 times
...
PMPStudent
1 year, 11 months ago
Selected Answer: A
They are not asking about what you should do NEXT. They are asking about measures to mitigate the impact. I believe A is the correct answer. Adding it to the risk register or informing the client WILL NOT reduce the impact of this situation. You want to make sure that when this key resource leaves, there are no gaps.
upvoted 2 times
...
arnibert
1 year, 12 months ago
From customer perspective I would see this as a risk and I would like to be informed about it? "Proactive knowledge sharing" is of course always a good idea as well but you would first need to hire the new knowledge receiving person, no? So my best guess would have been: 1. risk identification & documentation, 2. informing stakeholders, 3. plan mitigation activities (eg. knowledge transfer)...
upvoted 1 times
PMPStudent
1 year, 11 months ago
But they are not asking about what you should do NEXT. They are asking about measures to mitigate the impact. I believe A is the correct answer. Adding it to the risk register or informing the client WILL NOT reduce the impact of this situation. You want to make sure that when this key resource leaves, there are no gaps.
upvoted 4 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...