A project for Company A was successfully delivered within scope, schedule, and budget by the end of the last iteration. However, during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.
What should the project manager have done to avoid this perception?
Adeshola1960
Highly Voted 1 year, 8 months agoprokat_mashin_na_vicecity
11 months agomjs
Highly Voted 1 year, 10 months agoea4e1f8
Most Recent 2 weeks, 5 days agotonybuivannghia
2 months agoUppersquareCapital
5 months, 3 weeks agoBruce_Liu
7 months, 4 weeks agopsvexam
8 months, 1 week agojosephsafiran
8 months, 1 week agoOnly12go
11 months agovictory108
1 year agoAish_
1 year, 1 month agokevzzz
1 year, 1 month agoprokat_mashin_na_vicecity
11 months agoAstridN
1 year, 2 months agoSteAle
1 year, 2 months agoNeil20
1 year, 3 months agonoppy
1 year, 3 months agoemelba
1 year, 4 months ago