Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 394 discussion

Actual exam question from PMI's PMP
Question #: 394
Topic #: 1
[All PMP Questions]

An agile project is running activities to define the minimum viable product (MVP). During the session, the project manager identifies some mandatory regulations, but there is no consensus to include these regulations in the MVP because it may extend the duration of the project.
What should the project manager do?

  • A. Ask the project sponsor to add more time to the project.
  • B. Get commitment from the team to include all of the required regulations.
  • C. Share with the participants the need to focus only on product functionality.
  • D. Train the team on the new regulations as requested by management.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Ngho
1 month, 1 week ago
The best answer is B. Get commitment from the team to include all of the required regulations. Regulatory requirements are mandatory and must be complied with, regardless of their impact on the project's duration or scope. The project manager should work with the team to gain their commitment to include these regulations in the Minimum Viable Product (MVP), ensuring the project remains compliant with legal and regulatory standards. Failing to comply with mandatory regulations could lead to legal or financial risks, so this is non-negotiable.
upvoted 1 times
...
victory108
1 year, 3 months ago
Selected Answer: B
B. Get commitment from the team to include all of the required regulations
upvoted 1 times
...
SteAle
1 year, 4 months ago
Selected Answer: B
The regulations are mandatory.
upvoted 1 times
...
Hung3102
1 year, 7 months ago
Choose B. Option C, "Share with the participants the need to focus only on product functionality," is not an appropriate approach because mandatory regulations must be adhered to, regardless of the impact on the duration of the project. Option D, "Train the team on the new regulations as requested by management," is a good approach to ensure that the team is aware of the regulations' requirements. However, the project manager should still work with the team to determine how to include these regulations in the MVP without significantly impacting the project's timeline.
upvoted 2 times
Hung1
1 year, 6 months ago
https://www.examtopics.com/discussions/pmi/view/52882-exam-pmp-topic-1-question-2519-discussion/
upvoted 1 times
...
...
Yuuns
1 year, 8 months ago
B, regulations were "mandatory".
upvoted 3 times
...
rajeshtk
1 year, 8 months ago
It Should be C.
upvoted 1 times
...
meetkamal
1 year, 9 months ago
Selected Answer: C
Should be C
upvoted 1 times
...
mjs
2 years ago
Why B, should be C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...