During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels.

Which two actions should the project manager take first to address this conflict? (Choose two.)

  • A. Plan to resolve the team members' conflicts after the sprint and focus on achieving the goal.
  • B. Arrange individual meetings with the team members who cannot work together effectively.
  • C. Address the conflict during team meetings for the entire team to participate and find solutions.
  • D. Ask human resources (HR) to intervene before it escalates and affects the team's performance.
  • E. Discuss the conflict early among the affected team members using a direct, collaborative approach.
Show Suggested Answer Hide Answer
Suggested Answer: BE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
teslamaster
Highly Voted 1 year, 11 months ago
Selected Answer: BE
why not B &E ?
upvoted 10 times
...
Abdelmonm
Most Recent 8 months, 3 weeks ago
Selected Answer: BC
B. Arrange individual meetings with the team members who cannot work together effectively. C. Address the conflict during team meetings for the entire team to participate and find solutions. Individual meetings with the conflicting team members allow the project manager to understand their perspectives, concerns, and underlying issues. This information is crucial for devising effective strategies to address the conflict. Additionally, addressing the conflict during team meetings provides an opportunity for open communication and collaboration among the entire team, fostering a collective effort to find solutions and improve team dynamics. Combining individual discussions with broader team involvement helps create a more comprehensive and inclusive approach to conflict resolution.
upvoted 4 times
...
odylec
10 months ago
Selected Answer: CE
CE. E to discuss with the members about the problem and C to discuss with all the team about the technical part.
upvoted 1 times
...
Nassim_Paco
10 months, 3 weeks ago
AB is the good answer
upvoted 1 times
...
certificate988
10 months, 3 weeks ago
Selected Answer: BC
B is for conflict at interpersonal levels. C is for conflict at technical levels. E can't be option due to term 'early' and this option is not better than B. This option is not to resolve conflict at technical level.
upvoted 2 times
urso2703
6 months, 3 weeks ago
thanks for this explanation. My answer was BE but your reasoning makes it clear. I support this.
upvoted 1 times
...
...
victory108
1 year ago
Selected Answer: BE
B. Arrange individual meetings with the team members who cannot work together effectively E. Discuss the conflict early among the affected team members using a direct, collaborative approach
upvoted 1 times
...
Aish_
1 year, 2 months ago
Selected Answer: BE
Individual meetings with the team members involved in the conflict can provide a safe and private environment to understand the root causes of the conflict, gather perspectives, and explore potential solutions. This approach allows the project manager to gain insights into the specific issues and concerns of each team member. Discussing the conflict early among the affected team members using a direct, collaborative approach promotes open communication and encourages the team members to work together to find resolutions. Encouraging open dialogue can lead to a more constructive and respectful environment for addressing conflicts. Options A, C, and D might be considered later in the conflict resolution process, but the initial steps should focus on addressing the issues directly with the involved team members to foster a more productive and harmonious work environment.
upvoted 4 times
...
smartrammy
1 year, 3 months ago
Selected Answer: BE
B & E will be Correct options
upvoted 1 times
...
RevZig67
1 year, 6 months ago
Selected Answer: BE
By arranging individual meetings with the team members, the project manager can understand the root cause of the conflict and take appropriate action to resolve the issue. By discussing the conflict early with the affected team members using a direct, collaborative approach, the project manager can prevent the conflict from escalating and find a mutually acceptable solution.
upvoted 1 times
...
emelba
1 year, 6 months ago
Selected Answer: BE
BE are my choices
upvoted 1 times
...
JYKL88
1 year, 6 months ago
I will got for BC
upvoted 2 times
...
J_0234
1 year, 8 months ago
C & E is correct answer,
upvoted 1 times
...
Ragaa
1 year, 9 months ago
B and E will be Correct choices,
upvoted 2 times
...
PMPStudent
1 year, 10 months ago
Selected Answer: BC
I think BC is correct. E = An approach to handle FUTURE conflicts. E does not help as the conflict already occurred. E is good to avoid future conflicts. The other reason C is good because the team is having technical conflicts.
upvoted 1 times
tdipen22
1 year, 10 months ago
Your approach is headon. But you misinterpreted the sentence. It actually means not to wait until end of sprint and just act on immediately. Ans is B and E.
upvoted 3 times
PMPStudent
1 year, 10 months ago
I totally understand what you are saying. But the question is: "Which two actions should the project manager take first to address this conflict?" Please note the key word "THIS" in the sentence. Option E is something to prevent conflicts. The question is asking you to resolve the existing conflict at hand. The other thing I do not like about option E is the word "DIRECT". Force/Direct conflict resolution technique results in a win/lose situation. This technique is not the ideal approach. The question mentions that there are 2 different types of conflicts, first is the personal and the second is the technical. To resolve personal conflicts, you first connect one-on-one to understand the conflict and then gather ONLY the parties involved in the conflict to resolve the conflict. But, for technical conflicts, after understanding what the conflict is, the PM invites the entire team and come up with the best approach that most of the team agrees to. The given options are just bad option. Therefore, I am not sure if it is BC or BE
upvoted 6 times
Jamrock
1 year, 5 months ago
good catch BUT the fact they do not call out the technical aspect directly in answer C, best to go with B & E. also there could be more conflict (future) so to your point, best to work on future now ("future now" - an oxymoron or play on words?) and go with BC.
upvoted 1 times
Jamrock
1 year, 1 month ago
correction - B&E
upvoted 1 times
...
...
...
...
...
poohwinniewong
1 year, 10 months ago
Chose BE originally, but I think 'affected team members' of E are meaning those other team members, instead of the 2 team members. So better have whole team to discuss together.
upvoted 1 times
...
Bobbie30
1 year, 10 months ago
Exactly. BE are my choices as well.
upvoted 3 times
...
mjs
1 year, 10 months ago
Selected Answer: CE
I think it should be C or B with E
upvoted 2 times
Jamrock
1 year, 1 month ago
never C: C. Address the conflict during team meetings for the entire team to participate and find solutions: While team involvement is important for solving certain conflicts, addressing interpersonal conflicts in a team meeting might exacerbate tensions and create discomfort among team members.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago