A project manager has been selected to deliver one of an organization's key flagship solutions. Critical success factors include agility, market adaptation, and a quick response to market offerings.
What is one of the key activities that the project manager should undertake to ensure company success?

  • A. Request more funding from the project sponsor to hire additional skilled resources and to incorporate additional quality in the project delivery approach and outcome.
  • B. Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables.
  • C. Create a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives.
  • D. Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ljz
1 month ago
Selected Answer: B
This is the right answer. Given the project's focus on agility, adaptability, and responsiveness to market trends, the project manager should establish clear and achievable goals. Collaboration with the sponsor ensures a shared understanding of priorities and market realities, alignment between project plans and expectations, and flexibility to adapt plans based on evolving market trends.
upvoted 1 times
...
szady
10 months, 1 week ago
Selected Answer: B
SHould be B
upvoted 1 times
...
Lucky_Cindy
11 months, 3 weeks ago
Selected Answer: D
D. Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions
upvoted 1 times
...
Jng2
1 year ago
why not B?
upvoted 2 times
...
victory108
1 year, 1 month ago
Selected Answer: D
D. Conduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions
upvoted 1 times
...
Asakthi
1 year, 2 months ago
B. Review the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables.
upvoted 1 times
...
Trytrio
1 year, 7 months ago
Selected Answer: D
Log in D please
upvoted 4 times
...
Bobbie30
1 year, 10 months ago
Please why do you say so?
upvoted 1 times
...
YYemi
1 year, 11 months ago
Should be B
upvoted 2 times
leo_gold
1 year, 10 months ago
"market adaptation" I guess this key word make me go directly to D.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago