Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 663 discussion

Actual exam question from PMI's PMP
Question #: 663
Topic #: 1
[All PMP Questions]

An internal virtual team is meeting daily to review iteration progress, as well as to conduct other technical and follow-up calls with key stakeholders. The team seems to be disengaged.

How should the project manager approach this situation?

  • A. Reduce the number of internal and external meetings.
  • B. Schedule one-to-one meetings and team-building meetings.
  • C. Review team assignments and reduce the workload.
  • D. Give the team members a few days off to reduce stress_
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
KA90
Highly Voted 1 year, 10 months ago
Selected Answer: A
the team seems overwhelmed by the number of meetings, A seems to make more sense instead of scheduling more meetings, thoughts ?
upvoted 9 times
noppy
1 year, 3 months ago
Can you let me know where you find a implying of "the team is overwhelmed" in the question?
upvoted 1 times
aqz_111
1 year, 2 months ago
'disengage' is the response for overwhelmed
upvoted 1 times
...
...
...
RevZig67
Highly Voted 1 year, 5 months ago
Selected Answer: B
If the team is disengaged, the project manager should take steps to address the issue and improve team motivation. One way to do this is by scheduling one-to-one meetings with each team member to discuss their concerns, challenges, and goals. Additionally, scheduling team-building meetings can help improve collaboration, communication, and overall team morale. This can include virtual team-building activities or social events that allow team members to get to know each other better and build relationships outside of work.
upvoted 9 times
aqz_111
1 year, 2 months ago
No, in scrum, there is no hierarchy so daily review meeting should not be reported to scrum master. Therefore 'one-to-one meeting' is not correct --> B is out scrum master should remove disruption caused to the team so we should reduce the internal & external call. Any queries should be direct to scrum master. Therefore A is better
upvoted 2 times
...
...
Kim222
Most Recent 2 weeks, 6 days ago
Selected Answer: B
This is B
upvoted 1 times
...
Davard
7 months ago
Selected Answer: B
Logic says it's likely A. However, PMI best practice is likely B. By scheduling one-to-one meetings and team-building sessions, the project manager can create opportunities for open communication, address individual concerns, foster team cohesion, and re-engage team members in the project's goals and objectives. This approach allows for personalized interaction and can help identify underlying issues contributing to the team's disengagement.
upvoted 3 times
...
Trytrio
7 months, 2 weeks ago
Selected Answer: B
Should be B
upvoted 1 times
...
Abdelmonm
7 months, 3 weeks ago
Selected Answer: B
The most appropriate approach to address disengagement in a virtual team is to schedule one-to-one meetings and team-building meetings (Option B). This helps in fostering better communication, understanding individual concerns, and building a sense of unity among team members.
upvoted 1 times
...
cb4a6c4
9 months ago
Selected Answer: A
Disengaged team - help them to focus on their work by reducing the meetings. Question reads other technical and follow-up calls reducing which would help!!
upvoted 1 times
...
Deeski
9 months ago
Selected Answer: A
Actually, after reading the question more carefully, I would agree to reduce the number of meetings so the Agile team can do the work. The PM job as a Servant leader is to protect the team from distraction.
upvoted 1 times
...
Only12go
11 months ago
Selected Answer: B
B. Schedule one-to-one meetings and team-building meetings. One-to-one meetings provide an opportunity for team members to discuss their concerns, challenges, or feedback in a more personal setting. Team-building meetings can help in fostering collaboration, trust, and rapport among team members, especially in a virtual environment where face-to-face interactions are limited. Both of these approaches can help in understanding the reasons for disengagement and in finding solutions to increase engagement and productivity.
upvoted 1 times
...
adingmaki
11 months, 1 week ago
Look at it this way. They are already disengaged with different meetings. And the solution is meeting?
upvoted 1 times
...
adingmaki
11 months, 1 week ago
They are already disengaged with the current meetings. Team buildings fosters team work and used for conflicts.
upvoted 1 times
...
adingmaki
11 months, 1 week ago
B? That's a lot of meetings hahaha It's A.
upvoted 1 times
...
victory108
11 months, 3 weeks ago
Selected Answer: B
B. Schedule one-to-one meetings and team-building meetings
upvoted 1 times
...
miggykurkova
1 year ago
If the team is disangaged, team motivation should be improved.
upvoted 1 times
...
SteAle
1 year, 1 month ago
Selected Answer: B
First of all, the PM need to understand WHY the team is disengaged - scheduling 1-1 meetings wouldn't break the agile approach
upvoted 2 times
...
Thirukj
1 year, 3 months ago
Selected Answer: A
A is the answer
upvoted 2 times
...
PMPStudent
1 year, 9 months ago
Selected Answer: C
THe only best answer is C. A = You can reduce the number of external calls, but internal calls? You need daily standups. So, removing internal calls does not sound good. B = Schedule more meetings on top of existing meetings? Not a good idea. Plus, Team Building? Team collaboration is not the issue here. C = Why would team have daily external calls? Obviously for many reasons but one of the reasons is the workload. D = Is never an option.
upvoted 2 times
15rajanikanthhotie
1 year, 9 months ago
The problem is stakeholder not getting engaged properly, to engage them and to identify the root cause, the PM first have one to one meetings and team building activities for better co-ordination. So I support B.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...