Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 647 discussion

Actual exam question from PMI's PMP
Question #: 647
Topic #: 1
[All PMP Questions]

In a daily standup meeting, a developer indicates that a backlog item will not be delivered because they need to take an unexpected leave for the next couple of days. The backlog item is a prerequisite for a feature expected by users in the next sprint review.

What should the project lead do?

  • A. Work with the product owner to change the priorities in the sprint backlog.
  • B. Work with the product owner to inform the users that the feature is delayed.
  • C. Ask the development manager to provide a replacement for a couple of days.
  • D. Ask the developer to postpone the leave until the backlog item is delivered.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Franco11
Highly Voted 1 year, 9 months ago
Selected Answer: C
The solution will not be in informing about the delay nor prioritizing the backlog because the requirement is critical, so the best choice is to find a replacement.
upvoted 11 times
PMPStudent
1 year, 9 months ago
Finding replacements are never good options as the new resource has no domain or product knowledge and will need time to learn and be able to finish the task. The learning part for the new resource is a risk which I as a manager will will not take.
upvoted 2 times
AstridN
1 year, 2 months ago
Picked C but your input clarified it for me. Thankss
upvoted 1 times
...
...
...
Alizade
Highly Voted 1 year, 5 months ago
Selected Answer: A
A. Work with the product owner to change the priorities in the sprint backlog. In an agile project, when a developer is unexpectedly unavailable, the project lead should collaborate with the product owner to reassess and reprioritize the sprint backlog. This may involve redistributing work among other team members or considering alternative ways to complete the prerequisite backlog item. This approach maintains the project's flexibility and adaptability, ensuring that the team can continue working effectively and delivering value to users. Options B, C, and D do not take advantage of the agile methodology's adaptability and may result in unnecessary delays, disruption to the team, or a negative impact on the developer's well-being.
upvoted 5 times
...
Kim222
Most Recent 3 weeks ago
Selected Answer: A
this is ...A ..???????
upvoted 1 times
...
KennyMuffins
7 months, 3 weeks ago
Selected Answer: A
Textbook answer would probably be A. Real life answer would have to be C.
upvoted 2 times
...
Abdelmonm
7 months, 3 weeks ago
Selected Answer: A
By working with the product owner to change the priorities in the sprint backlog, the project lead can adapt to the unexpected leave and ensure that the team focuses on delivering the most valuable and crucial items in the current circumstances. This allows for flexibility in managing priorities based on the availability of team members and helps mitigate the impact on the sprint's overall goals.
upvoted 1 times
...
UppersquareCapital
8 months, 2 weeks ago
Selected Answer: A
A. Work with the product owner to change the priorities in the sprint backlog. By working with the product owner, the team can reassess priorities and possibly rearrange the sprint backlog to focus on delivering other high-priority items that can still contribute value in the upcoming sprint review. This allows the team to adapt to the unexpected absence and ensure that user expectations are managed effectively. It is generally not advisable to ask the developer to postpone leave, as personal circumstances should be respected, and the team should be capable of adjusting to such situations.
upvoted 1 times
...
Xavierk
9 months ago
A is a the best option option, as a sprint is timeboxed, introducing a replacement will only bring its own risk and delay delivery
upvoted 1 times
...
certificate988
9 months, 3 weeks ago
Selected Answer: C
A is no as PO does not work on sprint backlog. B is no as we simply don't decide to delay feature until all other options are exhausted. C is better choice as asking for replacement should be explored.
upvoted 4 times
...
Only12go
11 months ago
Selected Answer: A
Answer is A becuase Choosing option C, which involves asking the development manager to provide a replacement for a couple of days, comes with potential complications: Ramp-Up Time: Bringing in a replacement, especially on short notice, means that the new person would need time to understand the context, the technical details, and the work that has been done so far on the backlog item. This ramp-up time might be longer than the remaining time in the sprint, which could lead to further delays. Quality Concerns: A developer who is unfamiliar with the specific item might introduce errors or might not implement it in a way that aligns with the team's standards or the original vision for the feature. Team Dynamics: Introducing a new member, even temporarily, can affect team dynamics and communication, especially if the team isn't used to working with that person.
upvoted 1 times
...
ali514
11 months, 3 weeks ago
Selected Answer: D
option D may also be a feasible option, depending on the context. If the backlog item is a prerequisite for a feature that is highly anticipated by users, and if the developer's leave is not for an emergency, then it may be reasonable to ask the developer to postpone their leave until the backlog item is delivered.
upvoted 1 times
...
nemm235
11 months, 3 weeks ago
Selected Answer: C
As per my understanding - developer need to leave for couple of days unexpectedly. A. if change the sprint backlog. (developer will not available who will work.) B. inform the users that feature is delayed. (is come after the Option C) best option is. first ask the "development manager" (not developer) about replacement for couple of days because sprint backlog items are prerequisite for next sprint review. if replacement is not available then inform the users for delivery delay.
upvoted 1 times
...
victory108
11 months, 4 weeks ago
Selected Answer: A
A. Work with the product owner to change the priorities in the sprint backlog
upvoted 1 times
...
Aish_
1 year, 1 month ago
PO does not prioritize the sprint backlog. Its only the product backlog. Here only option is to be transparent on the delay in delivery due to team members absence
upvoted 2 times
...
aqz_111
1 year, 2 months ago
Selected Answer: B
Based on the question, the current sprint goal cannot be achieved, the fact has to be notified the stakeholder. so I select B. Adjust the priority of current spring backlog (Answer a) does not give any help
upvoted 1 times
cwilson91
1 year, 2 months ago
I think I'm still leaning toward A. Yes, the dev mentioned the goal can't be achieved, but why not try to work with the Product Owner to reprioritize and attempt to actually achieve the goal? Sprint Backlogs are the same thing as User Stories and are just a sub-item of a Product Backlog. Yes user stories are typically put together by the developers, but the Product Owner can work with the developers to make any needed adjustments then reprioritize the Sprint Backlog within the Product Backlog. The product owner controls the prioritization of the Product Backlog, which again, includes the Sprint Backlog. Don't get me wrong, I still think we need to inform the end-users/stakeholders. But we should be informing them that the feature MAY be delayed, not that it'll be absolutely delayed.
upvoted 1 times
...
...
kevzzz
1 year, 3 months ago
Selected Answer: B
Only the Developers manage the Sprint Backlog, so the Developers would need to be the one to make the decision on if it is feasible to change the work in the Sprint Backlog. Work with the product owner to work with the users.
upvoted 1 times
...
emelba
1 year, 3 months ago
Selected Answer: A
option A is the most appropriate choice as it focuses on adjusting the priorities in the sprint backlog in collaboration with the product owner to accommodate the absence of the developer and ensure the timely delivery of valuable features to the users.
upvoted 2 times
...
RevZig67
1 year, 5 months ago
Selected Answer: D
As the backlog item is a prerequisite for a feature expected by users in the next sprint review, delaying it could result in a negative impact on the project. The project lead should talk to the developer and ask if they can postpone their leave until the backlog item is delivered. This would help ensure that the project stays on track and that the feature is delivered as expected in the next sprint review. If it's not possible to postpone the leave, the project lead can explore other options such as reassigning the work to another developer or working with the product owner to adjust priorities.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...