Question #: 693
Topic #: 1
[All PMP Questions]

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

  • A. Explain to the stakeholder that these are the approved templates for the reports.
  • B. Ask the project team to review and modify all of these reports.
  • C. Ensure that the reports comply with the communications management plan.
  • D. Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Faozi
Highly Voted 1 year, 3 months ago
Selected Answer: C
When a key stakeholder claims that the reports sent by the project team are inadequate, the project manager should first prioritize open and effective communication to address the concern. In this scenario, option C would be the most appropriate course of action. The project manager should ensure that the reports comply with the communications management plan. Option D is not the most suitable choice since involving the sponsor at this stage might escalate the situation unnecessarily. It's best to try resolving the issue within the project team and with the stakeholder before escalating it to higher levels.
upvoted 9 times
...
19_80
Most Recent 4 weeks ago
Why option D, I do not see it makes sense, PM can not escalate the issue to a sponsor without ensuring that he/she runs out of the options
upvoted 1 times
...
urso2703
5 months, 3 weeks ago
Selected Answer: C
Answered C because: it is a Key Stakeholder. the person should be in the Communications management plan. so it is best to ensure that the communications management plan is aligned to what was agreed to initially and address the concern raised by the Key stakeholder. However, a part of me understands why its D, as the Sponsor will be best to meet the Key Stakeholder first and gather that understanding. then comes back to the PM for the actual reason/concern.
upvoted 1 times
...
victory108
11 months, 3 weeks ago
Selected Answer: C
C. Ensure that the reports comply with the communications management plan
upvoted 3 times
...
Aish_
1 year, 1 month ago
Selected Answer: C
Since the key stakeholder claims that the reports are inadequate, the project manager should first verify if the reports are in alignment with the agreed communications management plan. The communications management plan outlines the frequency, format, and content of project communications, including reports sent to stakeholders. By ensuring that the reports are in compliance with this plan, the project manager can confirm that the project team is following the approved communication protocols.
upvoted 2 times
...
Dawn6699
1 year, 3 months ago
Selected Answer: C
I don't think sponsor will care about it... C would be better
upvoted 2 times
...
emelba
1 year, 5 months ago
Selected Answer: C
C is the answer. Option D is incorrect because involving the sponsor to diffuse the situation should not be the first action to take, and the project manager should try to address the stakeholder's concerns first.
upvoted 4 times
...
emelba
1 year, 5 months ago
Selected Answer: C
WTF why D answer? I would go with C but this dump not seems reliable to me
upvoted 2 times
...
JYKL88
1 year, 5 months ago
C is the answer, The project manager should first ensure that the reports are complying with the communications management plan. If the plan outlines the required format and content of the reports, then the project manager should work with the project team to ensure that they are adhering to the plan. If the reports are not meeting the plan requirements, then modifications may be necessary. The other options may be appropriate later, but the first step should be to ensure that the reports are meeting the plan requirements.
upvoted 2 times
...
sanjiiv
1 year, 6 months ago
Selected Answer: C
C it is
upvoted 1 times
...
Bobbie30
1 year, 9 months ago
C is a better answer
upvoted 4 times
...
poohwinniewong
1 year, 9 months ago
Why C? Can see whether it is adequate from the communication management plan?
upvoted 1 times
...
mjs
1 year, 9 months ago
Selected Answer: C
C is a better answer
upvoted 4 times
...
KA90
1 year, 10 months ago
Selected Answer: C
C is correct, type of information is noted in the Communication management plan
upvoted 3 times
...
teslamaster
1 year, 10 months ago
Selected Answer: C
C is a better answer
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...