A verbal announcement is made that the new team member joining the Scrum team has limited mobility. The scrum master is aware that some team members are unsure how the dynamics of the team will change.
What should the scrum master do?

  • A. Create a stakeholder engagement plan
  • B. Design a communications management plan
  • C. Update the team charter accordingly
  • D. Set up a meeting to discuss accommodations the team will have to make
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
462729f
2 months ago
Selected Answer: C
The Team Charter in Agile/Scrum outlines team norms, values, and working agreements. Since a new team member with limited mobility is joining, updating the Team Charter ensures: The team dynamic is inclusive and supportive. Expectations around collaboration, accommodations, and support are clear. A culture of respect and adaptability is reinforced.
upvoted 1 times
...
DavidTri
9 months, 3 weeks ago
Selected Answer: D
this is just verbal information so PM need to setup a meeting to discuss with the team first to define the appropriate the solution
upvoted 1 times
...
victory108
1 year, 7 months ago
Selected Answer: D
D. Set up a meeting to discuss accommodations the team will have to make
upvoted 1 times
...
miggykurkova
1 year, 7 months ago
First discuuss with the team and then update charter
upvoted 2 times
...
GinniSingh
1 year, 9 months ago
Selected Answer: D
first discuss then update charter
upvoted 2 times
...
JYKL88
2 years ago
D, need to understand the needs before doing C
upvoted 3 times
...
Hung3102
2 years ago
The scrum master should set up a meeting to discuss accommodations the team will have to make for the new team member with limited mobility. This will provide an opportunity for the team to discuss any concerns they may have, identify any changes that need to be made to accommodate the new team member, and work together to create a plan that ensures the team's success. The scrum master should facilitate the meeting and ensure that all team members have an opportunity to participate.
upvoted 2 times
...
sanjiiv
2 years, 1 month ago
Selected Answer: C
C seems correct to me
upvoted 1 times
...
meetkamal
2 years, 1 month ago
Why not C ??
upvoted 1 times
...
KA90
2 years, 5 months ago
why not C
upvoted 1 times
Jamrock
1 year, 8 months ago
C. Update the team charter accordingly: A team charter defines the team's purpose, objectives, roles, and responsibilities. While it's important to keep the team charter up-to-date, updating it to accommodate a new team member's limited mobility might be too specific and not address the immediate concern of discussing accommodations and changes in team dynamics. Setting up a meeting for open discussion is a more direct approach.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago