A project manager is assigned to a building construction project. The project manager has taken an agile course and wants to use agile practices in the project.
What should the project manager do?

  • A. Choose the agile practices that can be implemented in this type of construction project and apply them
  • B. Hire a consultant to provide a second opinion about whether agile can be applied to a construction project
  • C. Review the stages of the project to allocate additional budget for agile resources
  • D. Assign a scrum master to the project to implement agile practices in the project
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ductrinh
1 week, 3 days ago
Selected Answer: A
lol without permission from executive so everything would come back to waterfall but again this is PMI test so i chose A
upvoted 1 times
...
Asakthi
7 months, 3 weeks ago
Selected Answer: A
A. Choose the agile practices that can be implemented in this type of construction project and apply them
upvoted 1 times
...
victory108
10 months ago
Selected Answer: A
A. Choose the agile practices that can be implemented in this type of construction project and apply them
upvoted 1 times
...
ktwin1973
11 months ago
Answer: A The project manager should first review the construction project to determine which agile practices can be applied in this particular context. Not all agile practices will be applicable to a construction project, and it's important to choose those that are appropriate. Once the applicable practices have been identified, the project manager can apply them accordingly to the project. Hiring a consultant or allocating additional budget for agile resources may not be necessary if the project manager has the necessary knowledge and expertise to apply agile practices appropriately. Similarly, assigning a scrum master may not be necessary if the project manager is already familiar with agile practices and can implement them without additional support.
upvoted 2 times
...
MattAnya
11 months, 2 weeks ago
The project manager does not have the power to hire a consultant; that is the business of HR. The selected answer, A seems correct.
upvoted 2 times
...
Solid_Jehuty
1 year ago
How can agile be applied to a building construction? I think they should hire a co sultant because that would be expert advice?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago