A new regulation has been approved that will impact the deliverables in the fourth phase of the project. The delivery is following an iterative approach and is currently completing the second phase. What should the project manager do next?
A.
Consult with the project sponsor to discuss a cost increase
B.
Acquire approval for an exception to the implementation of the new regulation
C.
Get approval for the additional budget from the steering committee
D.
Meet with subject matter experts (SMEs) to access the impact to objectives
I I think D is the right answer because he needs to speak with the SME's to get the the details that will be included in the document that will be sent to the stakeholders
This section is not available anymore. Please use the main Exam Page.PMP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
victory108
8 months agoPMPStudent
1 year, 4 months agoBobbie30
1 year, 4 months agoleo_gold
1 year, 4 months agoKA90
1 year, 5 months ago