Question #: 55
Topic #: 1
[All PMP Questions]

It is late at night on a weekend when a team member calls the project manager on the telephone. The team member is crying about the pressures of an upcoming deadline.
What should the project manager do?

  • A. Review the organization's human resources (HR) policy.
  • B. Empathize with the team member and discuss next steps.
  • C. Ask the team member to send their concerns in writing.
  • D. Schedule a meeting with the team member for the next work day.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
58e5964
Highly Voted 1 year, 2 months ago
Selected Answer: B
While B might be the answer as per PMI recommendation, the PM should also be allowed to have a personal/professional work life balance. The PM should be expected to be a cousellor for the team all hours of the day, including their own personal time. PMI should recognize this and allow the PM to draw a line with the employee. The best course should be to schedule a meeting with the team member the very next day to address their concerns.
upvoted 9 times
mdkhassan
1 year ago
Drawing the line/discuss the next day is the 2nd step, not the first step
upvoted 4 times
...
...
AP2023S
Highly Voted 1 year, 11 months ago
Selected Answer: D
I understand that everyone will think the correct answer is B, but in the real world it would be D. We're talking about a LATE NIGHT phone call on the WEEKEND! And for a deadline that certainly doesn't fall on Sunday but which can also be discussed on Monday when we return to the office...
upvoted 8 times
AbbasTaki
1 year, 10 months ago
Correct, but as a project manager you must show empathy to the project team. Asking them to join you in a meeting will seem like you do not care and just want to hang up the call. B. would discuss the next steps which should be a one-one meeting with the employee
upvoted 4 times
Sketchie
1 year, 6 months ago
Yes, the next step could be a one-on-one meeting but the PM must first empathize with the team member.
upvoted 2 times
...
...
...
Princessviv96
Most Recent 3 days, 5 hours ago
Selected Answer: D
Dis the correct approach, while I would emphasize with the team member, I did ask to have a formal meeting the next business day to discuss his/ her concern in detail.
upvoted 1 times
...
maya1
1 week, 5 days ago
Selected Answer: D
Late night is off work hours and shoul be discussed the next day.
upvoted 1 times
...
ChymKuBoy
1 month ago
Selected Answer: B
B for sure
upvoted 1 times
...
AjitZavade
1 month ago
Selected Answer: B
Empathize. even if its for 2 minutes
upvoted 1 times
...
K91
3 months ago
Selected Answer: D
This question isn't asking what the PM should do "next", but just asking what the PM should do. I see many comments saying "empathize first", but "first" is not what we should focus on here. Considering LATE NIGHT and WEEKEND, I think D is the correct answer.
upvoted 1 times
...
kavikris
4 months ago
Selected Answer: D
Answer D, schedule 1-1 next day, if the option 'B" just leaves at empathizing then thats a better answer but it also talks about next steps, no manager will take time in the midnight of a weekend to discuss next steps or find a solution
upvoted 1 times
...
vlxx
5 months, 3 weeks ago
Options A, C, and D either delay addressing the team member's concerns or are impersonal, which could lead to further frustration or stress for the individual.
upvoted 1 times
...
LotToLearn
6 months, 1 week ago
B is correct answer as its first small step
upvoted 1 times
...
BuviD
1 year, 2 months ago
Selected Answer: B
B. Empathize with the team member and discuss next steps.
upvoted 1 times
...
BuviD
1 year, 2 months ago
Selected Answer: D
D. Schedule a meeting with the team member for the next work day.
upvoted 1 times
...
Lhenica
1 year, 4 months ago
Selected Answer: B
Need performed emotional intelligence
upvoted 1 times
...
GabMonterey
1 year, 4 months ago
Selected Answer: B
B. As a leader you need to understand the feelings of your team.
upvoted 1 times
...
estimater
1 year, 5 months ago
option B , the key word here is whem the member cried so the PM has to perform some emotional intelligence
upvoted 1 times
...
Sketchie
1 year, 6 months ago
B. The PM must apply emotional intelligence and leadership skills in his approach with team members
upvoted 2 times
...
Asakthi
1 year, 7 months ago
Selected Answer: B
B- empathize with the team member is the part of team leader
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago