Question #: 252
Topic #: 1
[All PMP Questions]

During project initiation meetings, the project manager of a 9-month project states that a specific task would be out of schedule. At the project kick-off meeting, a key project stakeholder strongly objects, stating that this task is the key value of the project and should be completed on time.
What should the project manager do to reduce the chances of having a strong rejection from stakeholders during the project initiation stage?

  • A. Develop a stakeholder-by-stakeholder engagement assessment matrix.
  • B. Send a letter to the stakeholders to inform them about the project scope and start date.
  • C. Schedule meetings with key stakeholders in advance to gather feedback on the project scope.
  • D. Identify stakeholder rejection as a risk in the project risk register.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
rajeshtk
Highly Voted 1 year, 11 months ago
Stakeholder engagement assessment matrix comes in the planning process group. Here the question is about Initiation stage hence the correct answer would be "C"
upvoted 5 times
...
Deepssss
Most Recent 8 months, 3 weeks ago
Selected Answer: C
C is right answer
upvoted 1 times
...
mesacgon
11 months, 3 weeks ago
LA respuesta es C.
upvoted 1 times
...
estimater
12 months ago
Selected Answer: C
PM has to deal with the stakeholder so i am with option C
upvoted 1 times
...
victory108
1 year, 2 months ago
Selected Answer: C
C. Schedule meetings with key stakeholders in advance to gather feedback on the project scope
upvoted 1 times
...
Mydax
1 year, 2 months ago
Selected Answer: A
Knowing how to engage your stakeholders could reduce the possibility of them having strong objections.
upvoted 2 times
...
Thirukj
1 year, 4 months ago
C is the right
upvoted 1 times
...
yousef11
1 year, 5 months ago
A is the correct answer. the Q. about how should you reduce the chance for such issue
upvoted 2 times
...
vins_vins_vins
1 year, 5 months ago
I vote for C
upvoted 1 times
...
JMCCRAY
1 year, 5 months ago
Selected Answer: C
To reduce the chances of having strong rejection from stakeholders during the project initiation stage, the project manager should consider option C, which is to schedule meetings with key stakeholders in advance to gather feedback on the project scope. By involving key stakeholders early in the project planning process, the project manager can gather feedback on the project scope and gain a better understanding of stakeholder expectations. This can help the project manager identify potential issues and concerns before they become major problems.
upvoted 1 times
...
LuanND
1 year, 8 months ago
Selected Answer: C
voting for C
upvoted 1 times
...
Adeshola1960
1 year, 9 months ago
Selected Answer: C
C. Schedule meetings with key stakeholders in advance to gather feedback on the project scope. To reduce the chances of having a strong rejection from stakeholders during the project initiation stage, the project manager should schedule meetings with key stakeholders in advance to gather feedback on the project scope. This will give stakeholders the opportunity to provide input and raise any concerns they may have about the project, including the specific task that the project manager believes would be out of schedule.
upvoted 1 times
...
Arulanandam
1 year, 10 months ago
Selected Answer: C
Voting for C. There is no Stakeholder by Stakeholder engagement matrix as such. There can only be a stakeholder engagement matrix. Also Stakeholder engagement matrix is to be updated based on stake holder need of informations/reports. In this case it would be apt to say that discuss with stakeholders align on scope well in advance.
upvoted 3 times
pmp_237student
1 year, 10 months ago
What if u have 100 stakeholders?
upvoted 1 times
Thirukj
1 year, 4 months ago
what if there are 1000 Stakeholders ? , lets be realistic
upvoted 1 times
...
...
...
PMPStudent
1 year, 10 months ago
Selected Answer: C
Going with C as well
upvoted 2 times
...
arnibert
1 year, 10 months ago
Selected Answer: C
I think (A) is just not enough because it doesn't say what to do with it. (C) would help more. (A) and (C) together would be best.
upvoted 3 times
...
poohwinniewong
1 year, 11 months ago
Why not C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago